Choosing a factory looks like choosing a price, but in fact it decides who will carry three risks and how: quality risk (defects), time risk (a delayed season) and money risk (prepayment, frozen cash). The sewing price in an offer is visible at once, while the price of these risks is not written into it. The topic teaches you to bring different offers to one denominator and to price the risks, so that the decision rests on the full cost of the item in your warehouse, not on the price list.

The first question: own production, an outsourced factory, or a hybrid. An own workshop gives control and speed of rework but freezes money in equipment and people and works well only with steady load. An outside factory gives flexibility but hands over part of the control. A hybrid keeps the complex and urgent work in-house and gives routine work out.

The reasoning goes in three steps. First score the factory on the same criteria (a scorecard): quality, lead time, price, financial stability, compliance, and check red flags separately: one critical failure is not compensated by the sum of scores. Then bring offers to one base. “Cut-make-trim only” (CMT), “fabric and sewing at the border” (FOB) and “turnkey” cannot be compared on price directly. Example: sewing RUB 900, fabric RUB 1,400, trims RUB 120, delivery and duty RUB 180 and 3% defects give about RUB 2,680; a turnkey offer at RUB 2,550 plus RUB 180 delivery and 4% defects gives about RUB 2,840: the cheap-looking line turned out dearer. Finally put a price on risk: acceptance sampling (AQL) shows what defect level you will let through, a nearer site costs more but pays back in speed, and air freight pays when the delay of sea freight costs more than the speed-up.

Start with a list of criteria and weights on which factories can be compared, then collect the offers into one cost table. Typical traps: judging by one sample, comparing a sewing price with a turnkey price, believing that AQL 2.5% guarantees no more than 2.5% defects, and choosing by price without counting the cost of a missed deadline.

Key ideas

Scorecard and red flag

A scorecard turns an “impression” into a score: each criterion gets a weight, each factory a score from 1 to 5, and the total is a weighted sum. But a red flag (for example, no confirmed documents or a missed deadline last season) rules a factory out whatever the sum: a good price does not cure a critical failure.

A single comparison base

CMT, FOB and turnkey differ in who buys the material and who ships the goods. To compare, add everything missing to each one up to a single point, for example your warehouse: fabric, trims, logistics, duty, expected defects. Only then are the lines comparable.

AQL and the guarantee trap

AQL (acceptable quality level) sets a sampling rule: for example, for a lot of 1,201–3,200 units you sample 125 and accept up to 7 defective at AQL 2.5. If the real defect rate is 5%, the lot is still accepted in about 70% of cases. A sample does not guarantee a defect ceiling; it only lowers the risk.

The price of proximity

A nearer site costs more but the cycle is shorter: less money frozen and less unsold stock at season end. Illustrative example: an item costing RUB 2,000 at 24% annual rate and a cycle shortened by 60 days saves about RUB 79 in frozen cash, plus savings on markdowns. The sum of the gains is the maximum premium above which the switch does not pay.

Air or sea

Air pays when the margin lost to the delay exceeds the difference in freight. If the lot is 1,000 units, the difference is RUB 250 per unit (RUB 250,000), and a three-week delay at 50 units a week and a margin of RUB 2,500 costs RUB 375,000, air is better. But if part of the demand returns after delivery, the lost margin is smaller.

Denim scrap is counted by stage: a late percent costs more than an early one

Losses by stage: cutting 1%, sewing 3%, washing 4%, finishing 2%. “10% of scrap” as one number does not describe it: the good share from cutting to packing is 90.3%. Operations per garment RUB 1,733, per good garment RUB 1,894: the price of scrap is RUB 161 per garment. A percent of loss at washing is dearer than a percent at cutting because fabric and sewing are already invested in the garment before it. So in the contract ask for the yield of good items by stage, not a general scrap percent.

Formula: Yield of good items = Π (1 − stage loss); cost per good item = operation costs ÷ yield

What to do: Ask the factory for the yield by stage and compare the late stages separately.

Think first: Losses of 1, 3, 4 and 2%. Is the good share 90% or slightly more?

Answer: Slightly more: 90.3%, because the losses multiply rather than add.

One position of the materials card gives almost three quarters of the order

In an order for 1,200 garments there are eight positions worth RUB 1,622,470, but the shell fabric takes 71.4%. Haggling over the label and the thread is pointless: the pennies saved are smaller than the error of the fabric price. The surplus after rolls and minimum runs is RUB 18,648 (1.15% of the order), and there are 1 positions where the minimum run is larger than the need: the logo patch is needed in 1,236 pieces, 2,000 are ordered. Negotiation and supplier checks begin with the most expensive position, and the minimum runs of small items are agreed with a reserve for the next collection.

Formula: Share of a position = position sum ÷ order; surplus = ordered − need

What to do: Rank the positions of the card by order sum and spend negotiation time from the top down.

Think first: There are eight positions. Are negotiations run on all equally or started with one?

Answer: With one: the shell fabric gives 71.4% of the order of RUB 1,622,470.

A trial does not always pay off

A trial batch costs money: a markup for a small batch of RUB 32,625, extras of RUB 45,000 and four weeks of delay of RUB 105,600, RUB 183,225 in all, 10.5% of an order of RUB 1.74 million. The gain depends on the probability that the supplier lets you down: for an unknown one (30%, loss share 60%) the trial gives RUB 22,313, for one checked in person (3%, 25%) −RUB 174,661. So a trial is taken by supplier class, and a checked one needs only sampling inspection and staged payment.

Formula: Gain = p × λ × (C × d − Cₜ) − trial costs

What to do: Assess the supplier class by the check list and compare the probability of failure with the break-even one.

Think first: Trial costs RUB 183,225, the full order RUB 1.74 million. What share of the order goes to the trial and why is it not always worth paying?

Answer: 10.5% of the order. It is worth paying when the expected loss without a trial is larger: RUB 313,200 for an unknown supplier, only RUB 13,050 for a checked one.

Negotiation by article and single-source risk

There is no point discussing the factory’s total price until it is split into articles. Building the price from your own norms gives a should-cost of RUB 1,480.2 against a quote of RUB 1,720: a gap of RUB 239.8. At the same time check that the whole buy does not rest on one supplier: at shares of 45, 25, 15, 10 and 5% the concentration index is 0.300, and a failure of the largest costs 0.55 m RUB of expected margin. A factory whose quality is cheap but whose defects reach the customer costs more than it seems.

Formula: Gap = quote − should-cost; HHI = Σ share²

What to do: Ask the factory for the price breakdown and the time study; qualify a second factory on a small volume in advance.

Think first: The quote is RUB 1,720, the should-cost RUB 1,480. What factory profit does that mean at your norms?

Answer: About 30% on the subtotal instead of the built-in 12%: the factory’s norms most likely differ from yours.

How to work through it

  1. Settle the strategic question: own workshop, factory or hybrid, and for which items.
  2. Set the scorecard criteria and weights and a separate list of red flags.
  3. Score factories by the same rules, including lead times and the quality of past orders.
  4. Collect offers into one base: material, sewing, logistics, duty, expected defects.
  5. Choose the acceptance level (AQL) for the price of an error and check whether the sample would catch real defects.
  6. Compare a near and a far site by the maximum premium.
  7. For urgent orders compare air and sea by the cost of delay.
  8. Check against a defect control chart on first lots: is the process stable.

Where to start

Start with the factory scorecard, then bring quotes to one basis in the quote comparison, then price the risk: sampling inspection, nearer and farther factory, air or sea. Calculations of the topic in order: “Factory scorecard”, “Comparing quotes: CMT, FOB, full package”, “Sampling inspection and cost of defects”, “Far and near factory: break-even premium”, “Air or sea: does speeding up pay”, “Control chart: the defect share (p) and the means of measurements (X̄ and S) with rules and Cpk”, “Should-cost vs the factory quote”, “Supplier concentration risk (HHI) and expected loss”, “Cost of quality: prevention, appraisal, internal and external failure”, “Customer-supplied material vs factory-bought”. See also (their primary topic is another one): “Supplier terms: total cost of buying per unit of demand”, “Order path: confirmation, fill rate and lost sales”, “Micro-batch versus large: fixed costs, experience curve, break point”, “Denim: fabric consumption with shrinkage, the garment price by stage and the cost of defects at washing”, “A materials order from the swatch and trim card: need with losses and shrinkage, packing, minimum lot, surplus and order date”, “A trial batch at a supplier: when the trial pays off, what a mistake without it costs and at what probability of defects it breaks even”.

Calculations in this topic

  • Factory scorecard

    Compares 2–4 factories on the same criteria: a weighted score, red flags and the gap between first and second place. A red flag outranks the sum: a factory with a great price and failing quality must not win.

    Which factory is best on the same criteria and whether the leader has a red flag.

  • Comparing quotes: CMT, FOB, full package

    Brings factory quotes in different “packages” (cut and make only, with materials, full package) to one basis: the item price in your warehouse with brand materials, losses, logistics, one-off costs and the cost of money. Shows the gap to the target cost.

    Which quote is cheaper once brought to one basis and whether it meets the target cost.

  • Sampling inspection and cost of defects

    Shows how likely a lot is to pass inspection under a “sample n, accept c” plan at the real defect rate, how many defective items reach the customer and what that costs; you can compare with a tighter sample.

    Will the sample notice real defects and what missed defects cost.

  • Far and near factory: break-even premium

    Calculates how much more the nearer factory may cost than the far one for the switch to still pay: savings on money in transit, on markdowns from a later decision, on freight and delay risk. The result is sensitive to the unsold share, so a range is shown.

    How much more a nearer factory may cost for the move to still pay.

  • Air or sea: does speeding up pay

    Compares the air-freight surcharge with the margin it protects and the cash it frees earlier. Finds the number of delay days at which air pays.

    How long a sea delay justifies air freight.

  • Control chart: the defect share (p) and the means of measurements (X̄ and S) with rules and Cpk

    From batches builds a control chart of the share of defects or returns (p) or a chart of the means and the spread of measurements (X̄ and S), calculates the center line and the 3σ limits, finds signals by four rules and from the mean charts calculates the capability indices Cp and Cpk against your tolerance. The limits can be recalculated without the points beyond the limits.

    Whether the process is stable or a special cause has appeared and whether the process fits the tolerance.

  • Should-cost vs the factory quote

    Builds a “justified” sewing price from your own norms: materials with waste, trims and packing, time by time study (SAM) at the factory rate, overheads on labor and the factory profit. Compares it with the quote and shows the gap in money and percent, the profit the factory builds in at your norms and, if the factory disclosed the price breakdown, the article with the largest gap to negotiate.

    What the justified price of a piece is at your norms and in which article the factory quote is overstated.

  • Supplier concentration risk (HHI) and expected loss

    From the suppliers’ shares of the buy counts the Herfindahl–Hirschman index (HHI) and the effective number of suppliers, the expected margin loss if the largest fails (probability × share × margin × share of the season without supply) and compares it with the cost of a second source: the price surcharge on the moved volume.

    How concentrated the buy is, what a failure of the largest costs and whether a second source pays off.

  • Cost of quality: prevention, appraisal, internal and external failure

    Adds the four categories of quality cost, shows the cost of poor quality (COPQ: internal and external failure), the share of quality cost in revenue and the shares of the categories. Estimates whether extra prevention pays off at the expected reduction of defects: the annual effect, ROI and payback.

    What quality costs, how much of it is failure and whether prevention pays off.

  • Customer-supplied material vs factory-bought

    Compares two ways to supply fabric for a piece: the factory buys it itself and charges a markup, or you hand the fabric to the factory (a customer-supplied scheme) and bear logistics, the cost of paying early, insurance and possible losses above the norm. Shows the saving per piece and the break-even factory markup.

    What is cheaper: giving fabric to the factory or leaving the buying to it.

  • Supplier terms: total cost of buying per unit of demand

    Compares 2-4 suppliers not by list price but by total cost: minimum order and excess, a discount or retro bonus, prepayment and credit (cost of money), defects and returns, shortfall, consignment. Ranks with a risk premium.

    Which supplier is cheaper by total cost rather than list price and what its terms cost.

  • Order path: confirmation, fill rate and lost sales

    By units reconciles “ordered, confirmed, delivered, accepted”: the confirmation rate (CONF), fulfillment of what was confirmed, unit fill rate overall and on time, where most is lost and what the shortfall and lateness cost. OTIF by orders alongside.

    How much of what was ordered is confirmed, delivered and accepted, where most is lost and what it costs.

  • Micro-batch versus large: fixed costs, experience curve, break point

    Compares the unit cost and margin of a micro-batch and a large batch of one style: fixed costs for patterns and setup are spread over the batch, labor falls along the experience curve, material is dearer in a small batch. Finds the smallest batch from which margin reaches your target.

    How much a micro-batch costs against a large one and from which batch a style reaches the target margin.

  • Denim: fabric consumption with shrinkage, the garment price by stage and the cost of defects at washing

    The fabric consumption at the finished size, the shrinkage in length and width, other fabric losses, the price per meter and the cost of the stages with a defect rate (cutting, sewing with trims, washing, finishing, packing) give the fabric consumption with the shrinkage allowance. From them the garment price after each stage, the contribution of defects to the price, the shelf price and the price of one point of shrinkage are counted. It shows why a garment costs more than the sum of operations: a defect at a late stage carries all the price already invested. Shrinkage and defects depend on the fabric, the washing and the factory: put in the results of a trial batch; the default values are illustrative.

    How much fabric is needed with shrinkage, how much a garment costs after each stage and how much defects at washing and finishing sit in the price.

  • A materials order from the swatch and trim card: need with losses and shrinkage, packing, minimum lot, surplus and order date

    From the number of garments and a table of materials (consumption per garment, losses, shrinkage, price, packing, minimum lot, lead time) it counts the need for every item, the order allowing for the roll and the minimum lot, the surplus and its cost, the cost of materials per garment and the week by which the order must be placed. It shows where the minimum lot exceeds the need and pays for a surplus. Set the prices, packing and lead times from supplier offers; the default values are illustrative.

    How much of every material to order allowing for losses, shrinkage, the roll and the minimum lot, how much money goes into the surplus and by which week the order must be placed.

  • A trial batch at a supplier: when the trial pays off, what a mistake without it costs and at what probability of defects it breaks even

    From the size of the full order, the unit price, the prepayment, the size and markup of the trial batch, the trial costs, the delay, the probability of detecting a problem and a table of supplier classes (probability of failure and the loss share) it counts what the trial costs, what losses it prevents and at what probability of defects it pays off. It suits China and any other country: take the full unit cost with logistics and duty from the “Full cost of an imported garment” calculation.

    Whether the trial pays off: what it costs, what losses it prevents for your supplier class and at what probability of defects it breaks even.

Self-check questions

  • By which criteria and with what weights are factories scored?
  • Does the leader have a red flag that price does not offset?
  • Are all offers brought to one base, one point and one currency?
  • Are materials supplied to the factory, duty and expected defects included?
  • Would the sample catch a real 5% defect rate and what is the chance of accepting such a lot?
  • What premium can be paid for proximity so that the switch stays profitable?
  • What is the cost of a sea delay in lost margin and will part of the demand return?
  • Who holds the conformity document and who applies the marking?
  • What are the prepayment and the payment term and how do they affect working capital?

Knowledge check

Multiple-choice questions. The correct answer and the explanation follow each question.

  1. Losses by stage 1%, 3%, 4% and 2%. Of 1,000 cut garments the good ones are about…

    • A. 900
    • B. 960
    • C. 903
    • D. 990

    Correct answer: C. 903. The losses multiply: 903 garments (90.3%). 900 is obtained only with a plain sum of losses. Covered in: Denim scrap is counted by stage: a late percent costs more than an early one.

  2. Operations without scrap RUB 1,733, cost per good garment by operations RUB 1,011. What is the price of scrap per garment?

    • A. 1,733 ₽
    • B. 161 ₽
    • C. 1,894 ₽
    • D. 883 ₽

    Correct answer: B. 161 ₽. The price of scrap = cost per good item − operations without scrap = RUB 1,894 − RUB 1,733 = RUB 161. Covered in: Denim scrap is counted by stage: a late percent costs more than an early one.

  3. On which denim stage does one percent of scrap cost more?

    • A. cutting
    • B. sewing
    • C. finishing and packing (late stages)
    • D. the same everywhere

    Correct answer: C. finishing and packing (late stages). The later the stage, the more cost is already invested in the garment, so scrap there is dearer. That is why the factory must give the yield by stage. Covered in: Denim scrap is counted by stage: a late percent costs more than an early one.

  4. The materials order sum is RUB 1,622,470, the shell fabric RUB 1,159,200. What share does the shell fabric give?

    • A. 1.1%
    • B. 37.5%
    • C. 71.4%
    • D. 12.5%

    Correct answer: C. 71.4%. RUB 1,159,200 ÷ RUB 1,622,470 = 71.4%. An equal 12.5% per position would be right only if all positions cost the same. Covered in: One position of the materials card gives almost three quarters of the order.

  5. The patch is needed in 1,236 pieces, the minimum run is 2,000. How much goes to surplus?

    • A. 2,000
    • B. 1,236
    • C. 764
    • D. 800

    Correct answer: C. 764. 2,000 − 1,236 = 764 pieces; the remainder can be agreed for the next collection. The order of 2,000 is not the surplus. Covered in: One position of the materials card gives almost three quarters of the order.

  6. The markup for a small batch is RUB 32,625, extras of the trial RUB 45,000, margin lost because of the delay RUB 105,600. What are the trial costs that will not come back?

    • A. 105,600 ₽
    • B. 77,625 ₽
    • C. 183,225 ₽
    • D. 250,125 ₽

    Correct answer: C. 183,225 ₽. 32,625 + 45,000 + 105,600 = RUB 183,225. RUB 250,125 is the purchase of the trial items themselves, which sell and are not counted as a cost. Covered in: A trial does not always pay off.

  7. An order of RUB 1.74 million, a probability of failure 30%, a loss share 60%. What is the expected loss without a trial?

    • A. 522,000 ₽
    • B. 1,044,000 ₽
    • C. 313,200 ₽
    • D. 156,600 ₽

    Correct answer: C. 313,200 ₽. 0.30 × 0.60 × 1,740,000 = RUB 313,200: the probability is multiplied by the loss share and by the whole order. One probability or one share without the other gives an overstatement, and counting by the prepayment of RUB 870,000 is wrong: the loss includes the defects of the whole order. Covered in: A trial does not always pay off.

  8. For a checked supplier (probability of failure 3%, loss share 25%) the trial gives −RUB 174,661. What should be done?

    • A. Take the trial anyway: it is calmer
    • B. Order at once with sampling inspection and staged payment
    • C. Pay the whole sum in advance
    • D. Drop the supplier

    Correct answer: B. Order at once with sampling inspection and staged payment. The expected loss without a trial of RUB 13,050 is smaller than the trial costs of RUB 183,225. Protection is needed but a cheaper one: sampling inspection, staged payment, the right to refuse. Covered in: A trial does not always pay off.

  9. What must be built to negotiate with a factory by article rather than by total?

    • A. A weighted average price of the last three orders
    • B. The price of the nearest competitor
    • C. A should-cost from your norms: materials, SAM at the factory rate, overheads, profit
    • D. A volume discount

    Correct answer: C. A should-cost from your norms: materials, SAM at the factory rate, overheads, profit. The should-cost shows in which article the quote diverges from the norms. Covered in: Negotiation by article and single-source risk.

  10. Supplier shares are 45, 25, 15, 10 and 5%. What is HHI?

    • A. 0.300
    • B. 0.150
    • C. 0.600
    • D. 0.900

    Correct answer: A. 0.300. HHI = 0.45² + 0.25² + 0.15² + 0.10² + 0.05² = 0.300. Covered in: Negotiation by article and single-source risk.

  11. Prevention 0.8, appraisal 1.5, failures 2.4 and 3.1 m RUB. What is the cost of quality?

    • A. 5.50 m RUB
    • B. 7.00 m RUB
    • C. 9.30 m RUB
    • D. 7.80 m RUB

    Correct answer: D. 7.80 m RUB. Prevention + appraisal + internal and external failure. Covered in: Negotiation by article and single-source risk.

Common mistakes

  • Mistake: Judging a factory by one sample

    What it costs: The sample is sewn by the best master and the series is worse

    How to avoid: Check the series, past orders and acceptance of the first lot.

  • Mistake: Comparing a sewing price with a turnkey price

    What it costs: The cheap-looking line excludes material

    How to avoid: Bring everything to one base.

  • Mistake: Believing AQL 2.5% guarantees no more than 2.5% defects

    What it costs: A lot with 5% defects passes in about 70% of cases

    How to avoid: Look at the acceptance curve and use a stricter level for critical defects.

  • Mistake: Choosing by price without the cost of a missed deadline

    What it costs: The delayed season eats all the savings

    How to avoid: Put a price on each day of delay in lost margin.

  • Mistake: Ignoring red flags for the sake of price

    What it costs: Problems with documents or finances surface after prepayment

    How to avoid: A red flag rules a factory out until it is fixed.

  • Mistake: The factory is given one scrap percent for everything

    What it costs: Errors of late stages are not visible The price of scrap is RUB 161 per good garment.

    How to avoid: Agree the yield of good items by stage Fix the yield of good items by stage in the order terms and check it on a trial batch.

    What it looks like (illustrative figures): At losses of 1%, 3%, 4% and 2% the good share is 90.3%, not 90%.

  • Mistake: Taking a trial from every supplier out of habit

    What it costs: Paying for the markup and delay where the risk is small An extra 174,661 ₽ on every order at a reliable supplier.

    How to avoid: Count the gain of a trial by supplier class Take a trial where the probability of failure is above the break-even one and leave reliable suppliers sampling inspection.

    What it looks like (illustrative figures): A checked supplier (3%, 25%): the expected loss without a trial RUB 13,050, trial costs RUB 183,225, a gain of −RUB 174,661.

  • Mistake: Taking SAM from the factory’s word

    What it costs: The should-cost repeats its inflated norms An overpayment in every batch.

    How to avoid: Time it yourself A time study of the operations and your own marker.

    What it looks like (illustrative figures): A calculation “by the factory’s norms” always matches its quote.

Russia and the EAEU

In Russia and the EAEU choosing a factory comes down to three practical questions. First: conformity confirmation. Items sold in the EAEU must have a declaration or certificate under the Customs Union technical regulations (TR CU 017/2011 for apparel and footwear, TR CU 007/2011 for children’s products); find out who prepares the document, to whom it is issued and in what time. Second: marking in the Chestny ZNAK system. The code is obtained by the owner of the goods, and it can be applied at the factory or at your warehouse: agree where and at whose cost. Third: payment. Payments to foreign factories follow currency control rules (Federal Law 173-FZ): count time, bank fee and the risk of payment delay.

On import, the factory price is increased by import duty at the rate of the Common Customs Tariff and import VAT of 22%, and their base depends on customs value; for children’s products the 10% VAT rate applies subject to confirmation of the details (a guideline, check with a broker). Factories in China, Turkey, Uzbekistan and EAEU countries give a different balance of price, time and customs; compare them on a single base. Fix prepayment and payment terms in the contract and check the factory’s history.

Factories inside the EAEU (Belarus, Kazakhstan, Armenia, Kyrgyzstan) supply without import duty but with indirect taxes under Annex 18 to the EAEU Treaty: VAT is paid in the country of destination, an import statement and supporting documents are needed. The technical regulations TR CU 007, 017, 019 are uniform across the union. In Kyrgyzstan, tax benefits tied to the average salary apply to the garment industry from 01.01.2026 to 01.01.2030 (a guideline, verify). For supplies into Russia from other EAEU countries the marking codes for Russia are ordered by the Russian importer or producer under a toll scheme; check the procedure.

Categories and audiences

Apparel
Apparel allows a wide choice of factories: many CMT and turnkey options, but quality differs by group (knitwear, outerwear, tailoring). Score a factory by the specific product group and its equipment. Defects are most often in fit, seams and color, and the minimum lot per model sets the depth of the range.
Footwear
Footwear needs lasts, molds and tooling for each model and size, so the entry barrier and minimum lot are higher and switching factories costs more. Defects are more critical: sole, glue, symmetry of the pair. Check tooling and stage-by-stage quality control, and separate the sample from the series especially strictly.
Accessories
Accessories are often made in small lots at specialized workshops (leather goods, jewelry, headwear). Minimums are small but quality varies more and the material (leather, metal) sets the price. The main risk is instability between lots and the workshop’s lead times at season peak.
Kids
Children’s products need strict safety requirements (TR CU 007/2011): materials, trims, dyes, no small detachable parts. A factory without experience in children’s items and safety documents gets a red flag. Sizing by height and quick aging of the collection make deadlines critical.
Men
A suit and a coat involve many pressing and hand operations, a shirt has separate operations for collar and cuff. A factory without such a line will sew the item, but the fit will be different. So in a men’s scorecard the weight of “equipment and skill for the item” is higher, and the candidate is checked with a control lot, not a sample.
Women
For a women’s line the choice of factory is pressed by fragmentation: dozens of models in lots of, say, 150–300 pieces, delicate fabrics, prints, lining. The minimum lot per model and color, the changeover time on the line and experience with chiffon and viscose are checked. In the scorecard these criteria weigh more than the price per garment: a cheap factory with a minimum of 500 pieces turns the budget into leftovers.

Questions this topic answers

  • Which factory is better on the same criteria?
  • Which quote is cheaper on a common basis?
  • Will our sample notice real defects?
  • At what premium is the nearer factory still worth it?

Key measures and terms

Study first

What next

Related: “Production and import”, “Cash and working capital”, “Customs and regulation”.

Documents on this topic

Open interactively →