Production order control: incoming fabric inspection, TNA, in-line and pre-shipment inspections, claims

A review of how to run a production order from sample to shipment: the incoming fabric inspection by a points system, the calendar of stages (TNA) and checkpoints, the pre-production meeting, in-line inspections and the final one by AQL, pre-shipment documents, claims and penalties. It decides whether to accept a roll of fabric, whether the order is on time and whether the lot can be shipped while something can still be corrected.

Production, logistics, channels Brand and retail Verified: 2026-11-14

Open interactively →

Why this document

A missed deadline and fabric defects are usually noticed too late: when it is cut and sewn. It is cheapest to catch a problem at entry, dearer in the middle, dearest at the customer. The document gives the control order and the indicators (points per 100 square meters of fabric, the share of overdue milestones) by which a deviation is visible before shipment. It is read by the head of production, the technologist, the buyer and the quality controller. The point thresholds and tolerances are set by contract and the numbers in examples are illustrative; Russian norms on claim periods are marked unverified.

At a glance

What is this document and why is it needed?
A review of how to run a production order from sample to shipment: the incoming fabric inspection by a points system, the calendar of stages (TNA) and checkpoints, the pre-production meeting, in-line inspections and the final one by AQL, pre-shipment documents, claims and penalties. It decides whether to accept a roll of fabric, whether the order is on time and whether the lot can be shipped while something can still be corrected.
Who owns the document and how often is it rebuilt?
The head of production and the quality controller with the buyer; the order calendar is kept weekly and the performance report is submitted after shipment and enters the factory assessment.
What mistakes are the most common?
Accept fabric without incoming inspection → a defect is visible after cutting → a sample of rolls inspected and the point threshold in the contract. Keep the TNA “in the head” → a failure is visible on the day of shipment → a shared table, a weekly review and a traffic light. Run inspection only at the end → it is too late to correct → an in-line inspection at 20-50% of output.

For whom

Brand
A brand controls the order at the factory remotely or on site: accepts the fabric, agrees the calendar, runs inspections and decides on shipment. The main questions: fabric acceptance thresholds, critical milestones, the date of the last chance to correct, claims and penalties.
Retail
A retailer with a private label runs dozens of orders at different factories and keeps a common standard and calendar. The main questions: a traffic light for orders, tying shipment to the receiving windows of the distribution center, escalation of delays and recording claims by factory.

What it consists of

Incoming fabric inspection

  • Width, density, color and composition are checked on a sample of rolls before cutting; a mismatch in width and density changes consumption and weight, and the color of different lots shade variation which is visible on finished garments.
  • The four-point system rates defects by length: each defect gets 1 to 4 points and the roll points are converted to 100 square meters; the defect length limits and thresholds are set by your acceptance standard (unverified).
  • Shrinkage and a wash test confirm the expected change in size; the result goes into the consumption norm and tolerances; strength and abrasion are checked for outerwear, footwear and bags.
  • The decision on a roll: accept, accept with a discount or tighter control, return to the supplier; the decision and the deviation are recorded in an act and enter the claim under the supply contract.

TNA: the calendar of stages and checkpoints

  • TNA (time and action) is the order calendar with milestone dates: sample approval, fabric and trims acceptance, cutting, sewing, inspections, shipment; a person responsible is named for each milestone.
  • Critical milestones (fabric, trims, start of cutting) set the whole schedule; their delay by a week shifts shipment by the same week or more.
  • The order traffic light: green (all milestones on time), yellow (delay of non-critical milestones or a small one on critical), red (a critical milestone missed): escalation is connected to red.
  • The share of overdue milestones and the average delay show how well the order is performed to plan; their accumulated statistics enter the factory assessment (the “Sourcing” document).

Inspections and pre-shipment control

  • The pre-production meeting reconciles the sample, materials, norms, tolerances, schedule and risks before launch; without it the factory launches without understanding the requirements.
  • The in-line inspection takes place at 20-50% of output: fit, seams, hardware and the first deviations are checked while they can be corrected in the rest of the lot.
  • The final AQL inspection checks a sample of the finished lot by the sampling plan and the criteria of critical, major and minor defects (the “Quality control” document).
  • Pre-shipment documents: an acceptance act, a certificate or declaration, a packing list, marking; without them the lot cannot be released or accepted at the distribution center.

Claims, penalties and the performance report

  • A claim is made within the period of the contract with an act, photos, a sample and a calculation of damage; the period and procedure are set out in the contract and the law (unverified).
  • Penalties for missed deadlines and quality set the amount, the calculation procedure and the cap; a court may reduce unreasonably large penalties, so record the real damage.
  • The reference sample is kept by you and by the factory and serves as the standard in disputes about quality.
  • The order performance report: actual time against plan, defect share, claims, correction costs; it enters the factory assessment and the decision about the next order.

Brand: how to organize control

  • Introduce incoming fabric inspection by points and a threshold agreed in the contract; a roll does not go to cutting without an acceptance act.
  • Keep the TNA in a shared table and review it once a week; a milestone that has moved prompts the question of what else will move.
  • Plan the in-line inspection at 30% of output: errors found later are dearer to correct.
  • For remote control use video and photos by a checklist and an on-site inspector for large lots.
  • Keep photos and acts for each milestone and roll: a month later a dispute about quality will be decided by the archive and not by memory.

Retail: how to run many orders

  • Assemble a traffic light for all orders and factories and review the reds weekly with the head of buying.
  • Tie shipment to the receiving windows of the distribution center: a delay of a week often means a missed window and the warehouse instead of the shelf.
  • Introduce one template of the fabric acceptance act, the inspection report and the claim for all factories and keep a register of claims.
  • Review the list of factories by the share of overdue milestones, fabric defects and claims once a season.
  • Set up a single register of delay reasons by factory: a recurring reason matters more than a single failure.

Where the data comes from

Data sourceFields
Incoming fabric inspection acts: length, width, points by rollroll length, width, defect points, decision
TNA and factory reports: planned and actual milestone datesmilestone, plan, actual, owner, reason for delay
Inspection reports: sample, defects by class, decisionsample size, critical and major defects, result
The contract: thresholds, tolerances, claim periods, penaltiespoint threshold, tolerances, claim periods, penalty amount

How to build it step by step

  1. Step 1: Fix in the contract the point threshold for fabric, tolerances, the claim period and the procedure for deciding on a roll.
  2. Step 2: Draw up the order TNA with milestones from sample approval to shipment, assign owners and critical points.
  3. Step 3: Run incoming inspection of a sample of rolls: width, density, color, defect points, shrinkage; decide on each roll.
  4. Step 4: Hold the pre-production meeting: sample, materials, norms, tolerances, schedule and risks.
  5. Step 5: Every week reconcile the TNA with the facts, calculate the share of overdue milestones and update the order traffic light.
  6. Step 6: Run the in-line inspection at 20-50% of output and record deviations and corrections.
  7. Brand: Step 7: Run the final AQL inspection, check documents and marking and decide on shipment; in case of refusal record the reasons and correction times.
  8. Retailer: Step 7: Reconcile the shipment date with the receiving window of the distribution center; if there is a risk of missing the window start escalation in advance.
  9. Brand: Step 8: Make the claim on time with an act, photos and a calculation of damage and demand correction or a discount under the contract.
  10. Retailer: Step 9: Enter the results into the factory assessment and the decision about the next order and update the claims register.

Formulas

MeasureFormulasNote
Points per 100 square metersB = P × 100 / (L × W), where P is the sum of defect points of the roll, L the roll length in meters, W the width in metersCompare with the threshold from the contract; rolls of different widths are comparable only after conversion to 100 m².
Share of overdue milestonesD = the number of milestones with the actual later than the plan / the number of milestones × 100Calculate separately for critical milestones: one overdue critical one matters more than three non-critical ones.
Average delayZ = Σ max(0, actual − plan) / the number of milestonesIn weeks; shows how much is lost on average per milestone.

Formulas in notation

Points per 100 m²
B = P · 100 / (L · W)
The sum of defect points of the roll is converted to an area of 100 square meters.

Worked example

The order TNA: planned and actual weeks of milestones (weeks from sample approval; illustrative data)

MilestonePlan, weekActual, weekDelay, wkStatus
Sample approved000On time
Fabric accepted after incoming inspection451Delayed
Trims received550On time
Pre-production meeting660On time
Cutting started781Delayed
First in-line inspection9101Delayed
Sewing finished12142Delayed
Final AQL inspection13152Delayed
Shipment14162Delayed
Total: the average delay per milestone, wk, and the number of overdue milestones1.06 of 9

6 of 9 milestones are overdue (67%), shipment moved by two weeks: the fabric came a week late and sewing lost another week. A yellow or red decision depends on the receiving window: if it is missed the order is red.

Figures

The order calendar (TNA) by plan. The critical stages fabric, trims and cutting stand at the beginning and set the whole schedule.

StageStart, wkLength, wk
Sample and approval02
Fabric and incoming inspection22
Trims32
Pre-production meeting51
Cutting62
Sewing and in-line inspection84
Final inspection and shipment122
Points per 100 m² by roll and the threshold
Bar chart: Roll 1 14.7, Roll 2 22.8, Roll 3 12.6, Roll 4 45.5, Roll 5 15.4, Roll 6 3301020304050Roll 1Roll 1Points per 100 m²: 14.714.7Contract threshold: 3030Roll 2Roll 2Points per 100 m²: 22.822.8Contract threshold: 3030Roll 3Roll 3Points per 100 m²: 12.612.6Contract threshold: 3030Roll 4Roll 4Points per 100 m²: 45.545.5Contract threshold: 3030Roll 5Roll 5Points per 100 m²: 15.415.4Contract threshold: 3030Roll 6Roll 6Points per 100 m²: 3333Contract threshold: 3030points
  • Points per 100 m²
  • Contract threshold
Data as a table
MeasurePoints per 100 m²Contract threshold
Roll 114.730
Roll 222.830
Roll 312.630
Roll 445.530
Roll 515.430
Roll 63330

Points per 100 m² by roll and the threshold. Rolls above the threshold go to a discount or return; rolls of different length and width can be compared only after conversion to 100 m².

Order checkpoints. The earlier the point, the cheaper it is to correct a deviation; the final inspection is the last chance before the customer.

  1. Incoming fabric inspection → Pre-production meeting
  2. Pre-production meeting → In-line inspection
  3. In-line inspection → Final AQL inspection
  4. Final AQL inspection → Pre-shipment documents
  5. Pre-shipment documents → Shipment and performance report
  6. Shipment and performance report

Specifics by category

Apparel
Apparel: incoming fabric inspection by points, shade variation and shrinkage; the in-line inspection checks fit and seams and the TNA includes cutting and sewing by lines.
Footwear
Footwear: leather and sole, last, lasting and the glue seam are controlled; inspections go by stages and the TNA includes tooling and samples; flexing and abrasion tests are mandatory.
Accessories
Accessories: leather and hardware, edges and coloring are controlled; leather defect points are counted by hide area and hardware is checked for strength and coating.
Kids
Children’s: material and fastening safety, certificates and marking for each lot are added to control; the final inspection checks small details and cords.
Men
Men’s: suit fabrics and lining need careful incoming inspection and a symmetry check; fit tolerances are stricter and TNA times longer for sample fittings.
Women
Women’s: short runs and many colors give many fabric lots and a risk of shade variation; the calendar is tight and a shift of one milestone often breaks the receiving window.

Common mistakes

  • Accept fabric without incoming inspection → a defect is visible after cutting → a sample of rolls inspected and the point threshold in the contract.
  • Keep the TNA “in the head” → a failure is visible on the day of shipment → a shared table, a weekly review and a traffic light.
  • Run inspection only at the end → it is too late to correct → an in-line inspection at 20-50% of output.
  • Not making the claim on time → the right to claim is lost → know the periods under the contract and law and collect acts and photos at once.
  • Not keeping a performance report → factories are compared by feeling → record actual time against plan, defects and claims for each order.

Russian specifics

  • Claim periods and procedure are determined by the supply and work contract and the general norms of civil law; fix them in the contract and keep acts and correspondence (unverified).
  • Brand: a certificate or declaration of conformity and marking are completed before the lot is released to the market; the pre-shipment check includes their presence and conformity to the lot (unverified).
  • Retailer: acceptance of the lot at the distribution center is reconciled with the inspection acts and factory documents; discrepancies are recorded in an act on the day of receiving.
  • On-site inspection in CIS countries is simpler and cheaper than in far countries; for far ones a third-party inspection company and video audit are used (unverified: check the terms).

Open interactively →