Season calendar counted back from the shelf date
From the days to the shelf date and the chain of stages (development, samples, order, production, transit, customs and marking, warehouse) calculates the path length, the latest start day, the slack in the normal and the worst case and the cost of lateness in season margin.
At a glance
- What question does it answer?
- When to start to make the shelf date and what lateness costs.
- What data is needed?
- Days to the shelf date.
- How to read the result?
- On the default data (200 days to the shelf, seven stages) the chain is 173 days, the latest start is day 27 from today, the slack in the normal case is 27 days. In the worst case (the sum of spreads 39 days) the slack is minus 12 days, at the typical spread plus 10.8 days. The margin lost is 110,000 per day of delay, the cost of the worst case is 1,320,000. Example on the default values: Chain length: 173 days; Latest start day (from today): 27; Slack in the normal case: 27 days; Slack at the typical spread: 10.8 days. The figures are illustrative: enter your own to see your result.
Why and how to reason
A collection reaching the shelf is governed by the longest chain of work, and a delay at one stage shifts everything. The calculation runs backwards from the launch date. The sum of stage durations (concept 21, samples 35, fabric 30, production 45, transit 35, customs and marking 10, warehouse 7) is 183 days, but fabric ordering can start 10 days before samples end, so the chain is 173 days. There are 200 days to the shelf, so the latest start is in 27 days. Then we look at risk: each stage may slip (spreads 5, 7, 5, 10, 7, 3, 2). In the worst case the chain is 212 days and the delay is 12 days. Each day costs 30 million × 55% ÷ 120 × (1 − 20%) = 110,000, in total 1.32 million.
When to use it
Reach for it at the start of the season to see when you must begin and at every change of dates: expected delay at a factory, a new customs procedure. Do not use it as a detailed calendar: the calculation ignores parallel branches, and stage durations are your own. Assumptions: stages run in sequence with the given overlaps, spreads are independent, margin loss is even across the season.
How to read the result
Compare three slacks: normal case (27 days), typical spread (10.8 days) and worst (minus 12). If the worst slack is negative but the typical one positive, you live on the edge: find the stage with the largest spread (production) and agree terms for it. The cost of lateness of 1.32 million shows how much you can spend on speed (air freight, a second workshop). If the normal-case slack is already negative, the calculation says you are already late. Put the start date in the calendar with a margin and recalculate at every change of dates: the chain is long, and an error at an early stage eats all other margins.
Common mistakes
The usual mistakes: leaving out customs and marking, taking durations from the factory’s promises rather than from past seasons, counting overlaps that do not exist in practice. Do not simply add spreads: the typical spread is the root of the sum of squares. Do not skip stages that seem “internal” (approvals, samples for sign-off): they often take longer than production.
What data is needed?
- Days to the shelf date.
- The chain stages: duration, overlap and spread.
- Season sales, margin, season length and the recovered share of sales.
Inputs
| Field | Unit | Value in the example | Meaning |
|---|---|---|---|
| Days from today to the shelf date | days | 200 | The date by which goods must be on the shelf minus today’s date. The example value is illustrative. |
| Planned season sales excl. VAT | ₽ | 30,000,000 | Amount excl. VAT: the general rate is 22% from 01.01.2026 (law of 28.11.2025 No. 425-FZ, a guide as of 13.11.2026, check against the act text); 10% for children’s goods. Confirm the regime and rate with an accountant. |
| Length of the selling season | days | 120 | Days over which the planned sales accrue; stages BS, IS, AS and SO: before the sale, in the sale, after it and the final sell-out (your company may name them differently). The example value is illustrative. |
| Margin on sales | % | 55 | The share of revenue after cost. The example value is illustrative. |
| Share of lost sales recovered later | % | 20 | Some customers will wait for the goods: estimate from past delays. There is no single standard in Russia: enter your own figure. |
How it is calculated
| Step | Formula |
|---|---|
| Chain length | sum of durations − sum of overlaps |
| Latest start day | days to shelf − chain length |
| Worst case | length + sum of spreads; typical: length + root of the sum of squares |
| Cost of lateness | the smaller of (days late, season length) × margin lost per day |
Worked numbers
Default values from the app; in the interactive version you enter your own.
- Chain length
- 173 daysThe sum of durations less overlaps.
- Latest start day (from today)
- 27Zero or above: there is time. Below zero: you are already late by that many days.
- Slack in the normal case
- 27 days
- Slack at the typical spread
- 10.8 daysThe spread as the root of the sum of squares: valid if stages slip independently.
- Slack in the worst case
- −12 daysAll stages stretched by their full spread.
- Margin lost per day of delay
- 110,000 ₽Season sales × margin ÷ season length × (1 − recovered share).
- Cost of lateness in the worst case
- 1.32 m ₽Not above the season margin: days late are capped at the season length.
Data as a table
| Measure | Slack |
|---|---|
| Usual case | 27 |
| With typical spread | 11 |
| Worst case | −12 |
Schedule at the latest start (day from today)
| Stage | Start | End | Spread |
|---|---|---|---|
| Concept and sketches | 27 | 48 | 5 |
| Tech pack and samples | 48 | 83 | 7 |
| Order and fabric purchase | 73 | 103 | 5 |
| Production | 103 | 148 | 10 |
| Transit | 148 | 183 | 7 |
| Customs and marking | 183 | 193 | 3 |
| Warehouse and distribution | 193 | 200 | 2 |
In the worst case you are late by 12 days and lose about 1.32 m ₽ of margin: build in a buffer on the riskiest stages.
Even in the worst case the chain fits the deadline. Check that the stage spreads come from your past delays.
The longest stage: “Production” (45 days). A network of stages with several predecessors and slack for each: the “Collection calendar: critical path and slack” calculation. Allow for customs and marking in Russia from your own experience: check the rules and timing in the current text and with the broker.
Nuances and limits
- Take the spread from your own past delays rather than inventing it.
- Allow for the holidays of the factory country and your own in the durations.
- The worst case is conservative: all stages are late at once.
- A network with several predecessors is calculated in the “Collection calendar”.