Collection calendar (critical path) and lead time

The collection calendar schedules backwards from the on-shelf date every stage: trends, design, samples, preorder, fabric, production, inspection, transport and warehouse, with time buffers. It decides when to start development and which stage holds up the rest: a slip there moves the launch of the whole collection.

Commerce and buying Brand Verified: 2026-11-13

Open interactively →

Why this document

Seasonal timing cannot be caught up: if a collection lands a month late, part of the sales is lost for good and part goes out on discount. The calendar counts backwards from the launch date and finds the critical path: a chain of stages without slack, where each day of delay is a day of launch delay. The product director sees what to watch first, and the production planner builds a buffer into the riskiest stages, such as samples and transport. That is why the calendar is reviewed weekly, not once a season.

At a glance

What is this document and why is it needed?
The collection calendar schedules backwards from the on-shelf date every stage: trends, design, samples, preorder, fabric, production, inspection, transport and warehouse, with time buffers. It decides when to start development and which stage holds up the rest: a slip there moves the launch of the whole collection.
Who owns the document and how often is it rebuilt?
Brand: product director and production planner, per season, reviewed weekly; approved by the commercial director. Retailer: private-label buyer and logistics; for third-party brands it runs the delivery calendar and ship windows.
What mistakes are the most common?
Durations come from factory promises → a missed season → use actual durations from past seasons. No time buffer → any delay misses the shelf → set a buffer and check the critical path. Holidays and closures of factories and customs are ignored → stages shift → a calendar with country holidays.

For whom

Brand
A brand builds the full calendar from idea to shelf: development, samples, showroom and preorder, fabric, sewing, inspection, transport. Leading stages (fabric and samples) run in parallel, and production starts after orders are confirmed.
Retail
A retailer sees the calendar from the buying side: brand order windows, ship windows, cancel dates, warehouse receiving and store display. For private label the full development cycle is added.

What it consists of

Stages and durations

  • Brand: Trends and concept → design and tech pack → samples (prototype, fit, sealed sample) → showroom preorder → fabric and lab dips → production → AQL inspection → transport and customs → warehouse and distribution.
  • Brand: money in the calendar (Model B): one of two collections a year carries purchases of RUB 48.773 million excluding VAT (40,644 units at RUB 1,200). A 30% prepayment to the factory (RUB 14.632 million, an example condition: Model B sets the advance more modestly, see “Working capital”) is paid at order confirmation, i.e. at the end of the showroom stage 2027-06-01; the balance of 34,141 at AQL acceptance 2027-07-23. Money leaves 4 months before the shelf date.

Milestones

  • Brand: Concept freeze, sample approval, order close, fabric confirmation, production start, production release, warehouse arrival, on-shelf date.
  • Brand: Gates with the dates of the example: G1 Freeze of the concept and budget 2027-01-27; G2 Approval of the sealed sample 2027-05-02; G3 Order closing and factory prepayment 2027-06-01; G4 AQL acceptance and batch release 2027-07-23; G5 Arrival at the warehouse and marking 2027-09-16. Each gate has an owner and an exit condition (what must be ready): G2 requires a signed sealed sample and a confirmed price, G3 confirmed preorders not below plan and the prepayment under the contract.

Buffer and risk

  • Total time buffer and buffer per stage; the critical path: stages with zero float.
  • Brand: Risks: fabric delay, sample rework, customs, holidays at the factory location, FX shifts.

Brand: how the document differs and what to add

  • Brand: the critical path of the collection in the example: 8 stages without slack; parallel fabric and samples shorten the term by 30 days against the sequential plan.
  • Brand: the brand calendar is tied to the season window and to showroom and wholesale preorder dates: a showroom shift moves production and delivery.
  • Brand: samples pass prototype, fit and the sealed sample; each correction round adds 1 to 2 weeks and enters the contingency.
  • Brand: fabric booking and lab dips run in parallel with samples but before orders are confirmed: the brand accepts the risk of leftover fabric consciously.
  • Brand: production starts after orders are confirmed and fabric is ready; factory holiday stops are checked by date overlap.
  • Brand: AQL inspection before shipment and transport (sea, customs) take 45 to 52 days; air shortens the term but costs more and is recorded as a decision.
  • Brand: calendar cash: a collection carries a purchase of about RUB 48.773 million; the factory payment goes by stages (advance, balance) and the payment schedule is built into the calendar.
  • Brand: gates (G1 to G5) require decisions: concept freeze, sealed sample, order confirmation, shipment, warehouse receipt.

Retailer: how the document differs and what to add

  • Retailer: the retailer plans deliveries to the shelf date backwards: from the season start back through receipt, marking and distribution to stores.
  • Retailer: the purchasing calendar includes viewing and ordering from brands, the supplier’s production time and delivery to the distribution center.
  • Retailer: marking under the Chestny Znak requirements for categories where it is mandatory takes time at the warehouse and is part of the receipt stage.
  • Retailer: store openings and refurbishments are planned around the season: installation does not coincide with delivery of the seasonal collection.
  • Retailer: the retailer calendar includes price reductions and clearance by ladder; dates are agreed with the promotion plan and deliveries of the next collection.
  • Retailer: a supplier delay shifts the shelf: the retailer writes in advance the threshold after which an order is canceled or replaced by another model.
  • Retailer: the retailer calendar contingency covers customs and marking; no contingency leads to an empty shelf at the start of the season.
  • Retailer: the retailer calendar includes private-label production: samples, fabric booking and receipt follow the same scheme as a brand.

How to read the result and which decisions follow

  • Stage slack below 5 days (a guide) at several consecutive stages: the calendar is fragile, any delay shifts the shelf date; add buffer or move stages to parallel (start date in the example 2026-11-28).
  • A stage overlaps a factory holiday stop: move production before or after the stop or agree a schedule with the factory; the decision is made before order confirmation.
  • A critical stage is delayed by a week: decide whether to speed up (air, a second shift) at a cost or shift the shelf; without a recorded decision the calendar is not updated.

Where the data comes from

Data sourceFields
Development planStyles, stages, owners, statuses in PLM or a spreadsheet.
Factories and suppliersActual lead times from past seasons, OTIF, capacity constraints, holidays.
LogisticsTransport and customs times, warehouse receiving windows.

How to build it step by step

  1. Step 1. Fix the on-shelf date and the time buffer (in days).
  2. Step 2. Split the path into stages and enter actual durations from past seasons, not promises.
  3. Step 3. Compute dates backward from the shelf: the end of a stage = the start of the next.
  4. Brand: Step 4. Identify parallel stages (fabric runs in parallel with samples) and find the critical path.
  5. Brand: Step 5. Check holidays and closures of factories and customs; shift stages.
  6. Step 6. Set milestones with owners and exit conditions (what must be ready).
  7. Step 7. Compare actual and plan weekly; when behind, decide: speed up (air), cut volume, move the date.
  8. Step 8. After the season update actual durations for the next calendar.

Formulas

MeasureFormulasNote
Backward datesStage start = Stage end − Duration; Previous end = Stage startThe “Season calendar backward from the on-shelf date” calculation.
Total lead timeLead time = Σ durations of sequential stages + bufferParallel stages count by the longest one.
Stage floatFloat = Latest start − Earliest startZero float means the critical path.
Speed-up paybackBenefit = Days saved × Sales per day × Margin − Speed surchargeThe “Air or sea” calculation.

Formulas in notation

Early start and finish
ES_j = max_(i ∈ P_j) EF_i; EF_j = ES_j + d_j
P_j are the predecessors of stage j, d_j is its duration; the forward pass sets early dates.
Late finish
LF_j = min_(k ∈ S_j) (LF_k − d_k)
S_j are the successors of the stage; for the last stage LF equals the project length; a backward pass.
Stage slack
Slack_j = LF_j − d_j − ES_j
Zero slack means the stage is critical: any delay shifts the shelf date.
Start date
T_0 = T_shelf − (L + B)
T_shelf is the date on the shelf, L is the critical path length, B is the contingency buffer.

Worked example

A collection calendar with parallel stages and the critical path, on shelf 2027-10-01, buffer 15 days (on shelf: autumn 2027; money and the collection per Model B in the composition part)

StageDaysEarly startEarly endLate startFloat, daysCritical path
Trend research and concept602026-11-282027-01-272026-11-280yes
Design and tech pack452027-01-272027-03-132027-01-270yes
Samples: prototype, fit, sealed sample502027-03-132027-05-022027-03-130yes
Showroom, preorder and confirmation302027-05-022027-06-012027-05-020yes
Fabric booking and lab dips (parallel to samples)302027-03-132027-04-122027-05-0250no
Production452027-06-012027-07-162027-06-010yes
AQL inspection and packing72027-07-162027-07-232027-07-160yes
Transport (sea) and customs452027-07-232027-09-062027-07-230yes
Warehouse, marking, distribution to stores102027-09-062027-09-162027-09-060yes
Total: the longest path plus the buffer3072026-11-282027-10-0115

The longest path is 292 days plus a 15-day buffer: 307 days, development must start on 2026-11-28, 10 months before the shelf. The same stages in a row would take 337 days: ordering fabric in parallel saves 30 days. The critical path: Trend research and concept → Design and tech pack → Samples: prototype, fit, sealed sample → Showroom, preorder and confirmation → Production → AQL inspection and packing → Transport (sea) and customs → Warehouse, marking, distribution to stores; fabric booking has 50 days of float and is the only stage that can move without moving the shelf. Any delay of the sealed sample and the showroom moves the shelf one to one. Factory holidays (only factory stages are checked: samples, fabric, production, inspection; in the example the Chinese New Year downtime 2027-02-01 … 2027-02-21, a guide, not checked) do not overlap any stage; check the overlap for each factory and add downtime days to the stage duration. Air instead of sea saves about 38 days of transport, but it must be weighed against the markup and margin (the “Air or sea” calculation).

Figures

Collection calendar with parallel stages. Parallel stages shorten the term: fabric is booked at the same time as samples; critical stages with no slack are highlighted. The origin is the development start; the contingency buffer is added to the critical path separately.

StageStart, weeksLength, weeks
Trend research and concept08.6
Design and tech pack8.66.4
Samples: prototype, fit, sealed sample157.1
Showroom, preorder and confirmation22.14.3
Fabric booking and lab dips (parallel to samples)154.3
Production26.46.4
AQL inspection and packing32.91
Transport (sea) and customs33.96.4
Warehouse, marking, distribution to stores40.31.4

Stage links and the critical path. A stage does not start until its predecessors are done; the critical path determines the shelf date.

  1. Trend research and concept → Design and tech pack
  2. Design and tech pack → Samples: prototype, fit, sealed sample; Fabric booking and lab dips (parallel to samples)
  3. Samples: prototype, fit, sealed sample → Showroom, preorder and confirmation
  4. Showroom, preorder and confirmation → Production
  5. Fabric booking and lab dips (parallel to samples) → Production
  6. Production → AQL inspection and packing
  7. AQL inspection and packing → Transport (sea) and customs
  8. Transport (sea) and customs → Warehouse, marking, distribution to stores
  9. Warehouse, marking, distribution to stores

Specifics by category

Apparel
A typical cycle of 9-12 months; fabric and lab dips sit on the critical path; size samples and fit take several iterations; repeating basics shortens the path.
Footwear
The longest cycle (last, tooling, molds, samples across the size run); the footwear season starts before apparel, so the calendar starts 1-3 months earlier; sealed sample approval is critical.
Accessories
Different durations by group: bags (samples, hardware) take long, jewelry and hats are shorter; metal and leather have long lead times; certification is not needed for every group.
Kids
The calendar is tied to school (August deliveries) and winter; time for certification under TR CU 007/2011 and material checks is mandatory; the backward schedule is rigid because missing the school date means losing the season.
Men
Basics repeat, so the calendar is shorter and steadier; reorders on actuals are allowed; fit and size-run stability matter.
Women
More fashion and capsules, more sample iterations; the calendar includes several waves (drops), each needing its own critical path; quick response holds part of capacity in reserve.

Common mistakes

  • Durations come from factory promises → a missed season → use actual durations from past seasons.
  • No time buffer → any delay misses the shelf → set a buffer and check the critical path.
  • Holidays and closures of factories and customs are ignored → stages shift → a calendar with country holidays.
  • The sealed sample is approved late → rework in production → a milestone with an exit condition.
  • The calendar is not updated → drift from reality → a weekly check and correction.
  • Stage durations are taken from factory promises, not from the actuals of past seasons → the calendar shifts from the first stage → set actual durations and review after every season.
  • Parallel stages are not marked and the critical path is not found → the wrong things are sped up → compute the forward and backward pass and speed up only zero-float stages.

Russian specifics

  • Certification and declaration under TR CU 017/2011 and 007/2011 take time and must be in the calendar before shipment. Rule: CU Commission decision 876 of 09.12.2011: TR CU 017/2011 on safety of light-industry products (Customs Union Commission Decision of 09.12.2011 No. 876) (rule check not completed).
  • Chestny ZNAK marking requires codes to be put into circulation before sale; plan this stage before store distribution. Rule: Decree 1956 of 31.12.2019: Government Decree of 31.12.2019 No. 1956 (marking rules for light-industry goods) (rule check not completed).
  • Customs clearance and import VAT affect time and cash: put them into the calendar and budget. Rule: Tax Code Art. 160: Tax Code, Art. 160 (tax base on import) (rule check not completed).
  • The “warehouse and marking” stage: unmarked stock in the transition period is allowed only for storage, transport and marking for later sale, and stock not put into circulation in time loses its codes (decree 2129, the text was read in the register): plan the goods arrival and marking dates before these deadlines. Rule: Decree 2129 of 25.12.2025: Government Decree of 25.12.2025 No. 2129 (amendments to Decree No. 1956; fourth marking wave).

Open interactively →