Unit cost from the bill of materials

Builds the unit cost from a bill of materials: materials with waste, operations by factory minutes, overhead, defects, samples, logistics and duty. Then builds the price up to the shelf and shows where each rouble comes from.

Cost and price For whom: Brands, product and production managers before a style launches and when revisiting the price.

Calculate on your data →

At a glance

What question does it answer?
Which lines and in what proportion make up the unit cost and what shelf price results from it.
What data is needed?
The specification: materials with price, use and cutting waste; operations in minutes from a time study.
How to read the result?
Look not only at the total but at the composition: the share of materials and waste shows where to look for savings — in the pattern layout and fabric buying, while the share of operations points to time study and contractor choice. Check the shelf price against the market in the price position model. Example on the default values: A run of 1,500 units: unit cost RUB 2,170.64, materials 56.2% of cost and cutting waste RUB 111.91 per unit. Wholesale is RUB 4,823.64 excl. VAT, the shelf price RUB 11,769.68 incl. VAT and brand profit per run RUB 3,979,502. If the shelf price does not pass the market test, look for reserves in the biggest lines: fabric, sewing, defects. Next: “Price position among competitors” and “Allowable cost from the shelf price”.

Why and how to reason

A bill of materials (BOM) is the item’s recipe: what and how much is needed. The calculation follows the order in which the item is assembled. Materials: price x usage x (1 + waste). Operations: minutes x workshop minute rate. Added to overheads and duty on materials, they give direct costs. Defects are loaded on top of everything made: multiply by (1 + defect rate). Then samples per unit and logistics, which defects do not touch.

Next the price chain: wholesale = cost / (1 - brand margin), shelf with VAT by the same rules as in “Cost and price”.

Example. Materials RUB 1,220.91, operations (6 + 38 + 8 + 3) = 55 minutes x 14 = RUB 770. Direct 1,990.91, with a 3% defect rate 2,050.64, plus logistics 120: RUB 2,170.64. Wholesale 2,170.64 / 0.45 = RUB 4,824, shelf RUB 11,770, brand profit on a run of 1,500 about RUB 3.98 m.

When to use it

It comes in handy when developing a style and when recalculating cost after changes in materials or prices. Suitable for comparing design variants. Assumption: usage and time norms are accurate. For first samples they are approximate, refine after launch. It does not replace market price research. For imports add duty and the rate through “Landed cost”. Agree the BOM with the technologist.

How to read the result

The share of materials in cost (56%) shows where to look for savings: if materials give over half, haggle on fabric and cutting; if operations, look at design and time. Cutting waste per unit (RUB 112) is a reserve. Brand profit per run is the outcome for the run decision. Decision: compare BOM variants and choose the one that meets the shelf target and margin, not simply the cheapest one. Keep the BOM as a baseline: after materials change, recalculate and you will see exactly what got more expensive. This is faster than hunting for the cause in the final cost.

Common mistakes

Typical trap: applying the defect rate only to materials; ignoring samples; taking the minute rate without overheads; entering fabric usage without waste and then adding waste again. Also: not updating the BOM after changes. Also: not updating material prices, taking last year’s. Also: leaving out quality control costs.

What data is needed?

  • The specification: materials with price, use and cutting waste; operations in minutes from a time study.
  • The factory price per minute, defect rate, samples per run, logistics per unit; duty and overhead if any.
  • Target brand margin, retailer margin and VAT for the price chain.
  • Where to take it: materials from the item specification (price per unit from invoices, usage and waste from the marker); operations in minutes from the technologist’s time study; the workshop minute price from “Sewing price by workshop minutes”; defects, samples and logistics from loss records and sample costs. Margins and VAT from the pricing policy.

Inputs

FieldUnitValue in the exampleMeaning
Items in the rununits1,500How many items are in the run; materials, operations and samples are multiplied by it.
Factory price per minuteper minute14Sewing price ÷ minutes by time study; if you pay a fixed price per item, enter one operation row with 1 minute and put the item price here.
Factory overhead% of operations cost0If the factory bills it separately or you run your own workshop: rent, energy, supervisors.
Duty on materials% of materials cost0Only for imported materials; take the rate for the customs code from the broker.
Defects and losses% of direct costs3The share of direct costs you allow for defects and losses, from your own statistics.
Samples and patterns per run₽0One-off costs per style; spread over the run.
Logistics and packaging per unit₽120Logistics and packing per item.
Target brand margin at wholesale% of wholesale price55The share of the wholesale price left to the brand; the price chain is built from it.
Retailer margin% of retail excl. VAT50The share of the retail price excl. VAT the store keeps.
VAT%22The VAT rate in the shelf price; as of 13.11.2026 the main rate is 22% (Article 164 of the Tax Code). Check with your accountant.

How it is calculated

StepFormula
MaterialsΣ price × use × (1 + waste)
OperationsΣ minutes × price per minute
Direct costsMaterials + duty + operations + overhead
CostDirect × (1 + defects) + samples ÷ run + logistics
Wholesale, shelfWholesale = cost ÷ (1 − brand margin); shelf = wholesale ÷ (1 − retailer margin) × (1 + VAT)

Worked numbers

Default values from the app; in the interactive version you enter your own.

Unit cost
2,170.64 ₽
Materials in cost
56.2 %Together with duty on them.
Cutting waste per unit
111.91 ₽No colour: there is no standard waste figure in Russia, see the waste share in the table and compare with your own history.
Wholesale price (excl. VAT)
4,823.64 ₽
Shelf price incl. VAT
11,769.68 ₽
Brand profit on the run
3.98 m ₽If the whole run is sold at the wholesale price.
Unit cost by item
Waterfall: Materials (with waste) +1,221, Operations +770, Defects and losses +59.7, Logistics and packaging +120, Unit cost 2,17105001,0001,5002,0002,500Materials (with waste)Materials (withwaste)Materials (with waste): +1,221+1,221OperationsOperationsOperations: +770+770Defects and lossesDefects and lossesDefects and losses: +59.7+59.7Logistics and packagingLogistics andpackagingLogistics and packaging: +120+120Unit costUnit costUnit cost: 2,1712,171₽
  • positive
  • negative
  • total
Data as a table
StepChangeLevel
Materials (with waste)+1,2211,221
Operations+7701,991
Defects and losses+59.72,051
Logistics and packaging+1202,171
Unit cost—2,171

Cost breakdown

LinePer unitShare
Materials (with waste)1,220.91 ₽56 %
Operations770 ₽35 %
Defects and losses59.73 ₽3 %
Logistics and packaging120 ₽6 %

Cost 2,170.64 ₽: the shelf price at your margins is 11,769.68 ₽. Compare it with the market in “Price position among competitors”; if it does not fit, look for savings in the largest lines above.

Nuances and limits

  • Take use and waste norms from the pattern layout, not by eye: a 5% error on the main fabric often outweighs all the trims together.
  • Samples and patterns are one-off costs of a style: spread them over the real run, not the hoped-for one.
  • If materials are imported add duty; for the full cost of an import use the landed cost model.

Terms used