Container demurrage and standing: the sum for a delay, the price per garment and the payback of speeding up

From the days at the terminal and outside it, the free days and the rate steps it counts demurrage (stepped) and detention. It shows the sum for standing, the price per garment and its share of the garment’s cost, the cost of money for the days of standing and the price of the next day. It answers whether a paid speed-up (advance filing of documents, an urgent broker) pays off and at what delay. Set the rates and the free days from the carrier’s offer; the default values are illustrative.

Production and import For whom: Logisticians, buyers and CFOs who count the price of a container delay at the terminal and decide whether to pay for speeding up.

Calculate on your data →

At a glance

What question does it answer?
How much container standing costs after the free days, how much that is per garment and whether a paid measure that cuts the days at the terminal will pay off.
What data is needed?
The number of garments in the container and their cost in the warehouse.
How to read the result?
Example on the default values (800 garments, 7 free days, 17 days at the terminal): 10 days beyond the term, demurrage RUB 39,000, detention RUB 5,000, total RUB 44,000, per garment RUB 55 (5% of the cost). Speeding up by 3 days for RUB 15,000 gives a gain of RUB 18,000, the net result RUB 3,000. Example on the default values: Days beyond the free time at the terminal: 10; Demurrage at the terminal: RUB 39,000; Detention outside the terminal: RUB 5,000; Total for standing: RUB 44,000. The figures are illustrative: enter your own to see your result.

Why and how to reason

Shipping is usually compared by the rate per container, while money is lost on the days when the container stands. The line and the terminal have a free time, after it every day is paid and the rate rises in steps: the longer the standing, the dearer the next day. So the sum is not proportional to the delay. Demurrage is paid for a loaded container at the terminal, detention for the line’s container at your place until it is returned empty. The calculation counts the days beyond the term separately at the terminal and at the consignee, sums the rate of each day by step, divides the sum by the number of garments and compares it with the cost of one. At the default values 7 days are free, 17 at the terminal, that is 10 paid: 7 days at 3,000 and 3 days at 6,000 give 39,000, detention adds 5,000. In all 44,000, or 55 per garment, about 5% of the cost of 1,100.

When to use it

Apply before ordering the shipping and when there is doubt about the release or receipt times: when the cargo may get stuck at the terminal, when there is no unloading slot, when marking or documents are not ready. It does not fit if the terms of the line are not known: the free days and the steps are taken only from the offer. For footwear, accessories and children’s the standing sum is the same, the batch volume and the cost change and so the share of the price of a garment.

How to read the result

Look at three numbers: the sum for standing, the price per garment and the price of the next day. If the sum is less than the price of speeding up, there is no need to speed up; if it is more, the measure pays off. The indicator “pays off if the delay is at least” says at what number of paid days speeding up is already worthwhile: at the default values from 9 days. The share of the garment’s cost shows how much standing eats the margin: a few percent are already noticeable. The next step: check which of the days can be removed (documents, a warehouse slot, marking in advance) and put a reserve for delay into the landed cost of the batch.

Common mistakes

The rate of the first step is taken for all days: after it the day is dearer. Detention is forgotten: the container waits after release too. Calendar days are counted while the offer counts working ones or otherwise. Illustrative rates are taken as fact: the free days and steps differ between lines and terminals. Speeding up is compared with the sum for the whole delay and not with the days that the measure really removes.

What data is needed?

  • The number of garments in the container and their cost in the warehouse.
  • The free days and the steps of the demurrage and detention rates from the line’s or the terminal’s offer.
  • The actual days at the terminal and at the consignee, the cost and the effect of speeding up.

Inputs

FieldUnitValue in the exampleMeaning
Garments in the containerunits800How many garments travel in this container: the standing sum is divided by them. The example value is illustrative.
Cost of a garment in the warehouse₽1,100The full cost of a garment in the warehouse without VAT: the price of standing is compared with it. For footwear, accessories and children’s take your own. The example value is illustrative.
The company’s cost of money%12The annual rate: how much it costs to hold money in goods that stand and do not sell. The example value is illustrative.
Free days at the terminaldays7The term from the line’s or the terminal’s offer during which a loaded container stands free. The example value is illustrative.
Days at the terminal in factdays17How many days the container will stand before removal: from arrival to release and pickup. Take a reserve for checks and documents. The example value is illustrative.
Free days at the consigneedays5The term during which the line’s container can be kept free of charge until it is returned empty. The example value is illustrative.
Days at the consignee in factdays7How many days the container is with you: unloading, waiting for a warehouse slot, return. The example value is illustrative.
Detention rate per day₽2,500The charge per day beyond the free term outside the terminal, from the line’s offer. The example value is illustrative.
Cost of speeding up₽15,000How much a paid measure costs: advance filing of documents, an urgent broker, a night receipt. The example value is illustrative.
How many days at the terminal it cutsdays3By how many days less the container will stand at the terminal if the measure is applied. The example value is illustrative.

How it is calculated

StepFormula
Days beyond the termo = max(0; days at the terminal − free days)
DemurrageΣ over days 1…o of the step rate of that day
Detentiondays beyond the term outside the terminal × the rate per day
Per garment(demurrage + detention) ÷ garments
Payback of speeding updemurrage(o) − demurrage(o − saved days) against the cost of the measure

Worked numbers

Default values from the app; in the interactive version you enter your own.

Days beyond the free time at the terminal
10
Demurrage at the terminal
39,000 ₽
Detention outside the terminal
5,000 ₽
Total for standing
44,000 ₽
Per garment
55 ₽
Share of the garment’s cost
5 %
Cost of money for the days of standing
3,472 ₽
Price of the next day of standing
6,000 ₽The demurrage rate for the next day after the current delay.
Gain from speeding up before its cost
18,000 ₽How much demurrage will not have to be paid if the days at the terminal are cut.
Net result of speeding up
3,000 ₽
Speeding up pays off if the delay is at least, days
9
Demurrage by days beyond the free time
Line chart: Cumulative demurrage: 0 → 99k020k40k60k80k100k05101520Cumulative demurrage, 0: 0Cumulative demurrage, 20: 99k₽Days beyond the free time
Data as a table
Days beyond the free timeCumulative demurrage
00
13,000
26,000
39,000
412k
515k
618k
721k
827k
933k
1039k
1145k
1251k
1357k
1463k
1569k
1675k
1781k
1887k
1993k
2099k
What the sum for standing consists of
Bar chart: Demurrage 39k, Detention 5,000, Money in goods 3,472010k20k30k40kDemurrageDemurrageSum: 39k39kDetentionDetentionSum: 5,0005,000Money in goodsMoney in goodsSum: 3,4723,472₽
Data as a table
MeasureSum
Demurrage39k
Detention5,000
Money in goods3,472

Demurrage by steps

From dayDaysRate per daySum
173,000 ₽21,000 ₽
836,000 ₽18,000 ₽

The container stands at the terminal 10 days beyond the free time: every next day costs 6,000 ₽.

The calculation is simple: days are whole, the rate is taken by the step of the day. The terms of lines and terminals differ (how weekends are counted, from which moment the term runs, whether there is a common term for demurrage and detention): check the offer. For footwear, accessories and children’s the standing sum is the same but the share of the garment’s cost differs: take the cost of your category.

Nuances and limits

  • Counting the standing sum by the first rate step: after it every day costs more.
  • Ignoring detention: the container waits after release too until it is returned empty.
  • Taking illustrative rates as fact: the free days and steps differ between lines and terminals.

Terms used