Production load plan
Matches orders against factory capacity: how many standard minutes are needed, how many available, load, the timing of each order and how many extra workers or overtime hours are required.
At a glance
- What question does it answer?
- Whether capacity is enough for the orders within the chosen time and what to do if not.
- What data is needed?
- Capacity: workers, days, hours, lost time, efficiency.
- How to read the result?
- A load above 100% means the orders do not fit the horizon. The calculation shows how many workers or overtime hours are missing and the order completion by day. Example on the default values: 40 workers, 22 days, 8 hours, 25% lost time and 80% efficiency: capacity is 253,440 minutes a month; the orders need 552,000 minutes. Load over 3 months is 72.6%, all orders are completed in about 48 working days and no workers are missing. If load is above 100%, the calculation shows how many workers or overtime hours are missing and the finish schedule by order. Next: “Cut-and-make price from factory minutes (CM)” and “Collection calendar: critical path and slack”.
Why and how to reason
A workshop is a limited resource of time, so orders are compared not in pieces but in minutes. Each item has a standard time (SAM). The sum of quantity x SAM over orders is the need in minutes. Available minutes are computed as workers x days x hours x 60 x (1 - loss) x efficiency.
Load = need / available minutes over the horizon. A load above 100% means you will not manage: you need additional workers or overtime. Order time = order minutes / daily capacity.
Example. Worker capacity 22 x 8 x 60 x 0.75 x 0.8 = 6,336 min a month, workshop 40 x 6,336 = 253,440. Orders: 4,200 x 55 + 6,500 x 30 + 9,000 x 14 = 552,000 min. Over three months 760,320 are available, load 72.6%. Daily capacity is 11,520 min, so all orders take 47.9 working days.
When to use it
Reach for it when accepting orders and planning launch, to promise honest lead times. Suitable for a workshop and for assessing a contractor. Assumption: SAM norms are confirmed by time studies, efficiency is known. It does not account for sequence and small changeovers: with many short styles real losses are larger. A load of 100% on paper does not mean you will make it. Recalculate when the line composition changes.
How to read the result
Load in percent shows the headroom: 70-85% is usually a comfortable zone, but you have your own norms. Above that the risk of missing dates in case of breakdowns and illness is high. Compare the completion time in working days with the delivery date. If “missing workers” is above zero, decide: hire, offer overtime or pass part of the orders to a contractor. Decision: accept the order if load with it does not exceed the norm, or propose a different date. See which order gives the largest contribution to minutes: it is sometimes better to turn down a labor-intensive style with a low price than to expand the workshop.
Common mistakes
Counting hours without losses; using ideal SAM with 100% efficiency; ignoring holidays and leave; including in capacity workers who are on other lines. Also: ignoring preparatory operations (cutting). Also: adding workers without allowing for training time, so the result does not appear at once.
What data is needed?
- Capacity: workers, days, hours, lost time, efficiency.
- Orders: quantity and standard minutes per item (SAM), in launch order.
- The planning horizon in months.
- Where to take it: workers, days and hours from the workshop schedule and timesheet; losses and efficiency from output records of the previous period; orders and minutes per unit (SAM) from the order plan and technology cards. Enter orders in launch order, then set the horizon.
Inputs
| Field | Unit | Value in the example | Meaning |
|---|---|---|---|
| Workers on the line | people | 40 | How many people work on the line. |
| Working days a month | days | 22 | Working days per month excluding days off and downtime. |
| Productive hours a day | hours | 8 | Productive hours per day per person before lost time. |
| Lost time | % | 25 | The share of time lost to downtime and changeovers; count it here, not in efficiency. |
| Line efficiency | % | 80 | How the line performs relative to the norm; do not duplicate lost time. |
| Planning horizon | months | 3 | The time within which all orders must be completed. |
How it is calculated
| Step | Formula |
|---|---|
| Worker capacity per month | Days × hours × 60 × (1 − losses) × efficiency |
| Factory capacity | Workers × worker capacity |
| Load | Σ(quantity × minutes) ÷ (monthly capacity × horizon) |
| Order time | Order minutes ÷ capacity per day |
Worked numbers
Default values from the app; in the interactive version you enter your own.
- Load over the horizon
- 72.6 %Standard minutes of orders ÷ standard minutes of the factory over the horizon.
- Capacity per month
- 253,440 std minMinutes the factory delivers at the given losses and efficiency.
- Minutes needed by orders
- 552,000 std min
- Time to complete all orders
- 47.9 working daysHorizon 66 working days.
- Extra workers needed
- 0To fit the horizon without overtime.
- Or overtime hours
- 0 h
Launch schedule
| Order | Minutes | Duration, days | Start, day | End, day |
|---|---|---|---|---|
| Jackets | 231,000 | 20.1 | 0 | 20.1 |
| Dresses | 195,000 | 16.9 | 20.1 | 37 |
| Knitwear | 126,000 | 10.9 | 37 | 47.9 |
The factory is 73 % loaded over 3 months: all orders fit.
Nuances and limits
- Orders run one after another: parallel lines and changeover are not accounted for.
- Changeover and idle time between models are not counted: if they are large, add them to lost time.