Tender bid floor and reduction from the starting price

From cost and the target margin counts the lowest bid price and the permissible reduction from the starting maximum price, adds the cost of the bid and performance security and shows at which reduction the tightened requirements switch on. Percentages, terms and thresholds are entered by you with a check date.

Wholesale terms and credit For whom: Public procurement managers and commercial directors of suppliers.

Calculate on your data →

At a glance

What question does it answer?
The price below which not to go and what the security costs.
What data is needed?
Starting price, cost, target margin.
How to read the result?
The price floor with security, the permissible reduction and the regime at your bid. Example on the default values: Price floor: RUB 4.24 million; Permissible reduction from the starting price: 15.2%; Cost of bid security: RUB 904; Cost of performance security: RUB 55,000. The figures are illustrative: enter your own to see your result.

Why and how to reason

A bid price cannot go below the floor. In the example the starting price is 5 m RUB, cost 3.9 m RUB, margin 8%: the floor is RUB 4,239,130, the permissible reduction 15.2%; with security the floor is RUB 4,299,896. Percentages and thresholds are entered by you with a date.

When to use it

Apply before submitting a bid in a procurement. Check the requirements with a procurement specialist.

How to read the result

Look at the floor with security and the regime at your price: a deep reduction switches on tightened requirements.

Common mistakes

They cut the price below the floor to win and do not count the cost of security.

What data is needed?

  • Starting price, cost, target margin.
  • Bid and contract security, terms.
  • The special measures threshold.

Inputs

FieldUnitValue in the exampleMeaning
Starting maximum price₽5,000,000The price from the procurement notice. The example value is illustrative.
Your cost of performance₽3,900,000All costs of performing the contract, without security. The example value is illustrative.
Target margin%8The profit share in the bid price. The example value is illustrative.
Planned bid price₽4,500,000Optional: checks the margin and the dumping regime. Empty or 0: the check is skipped. The example value is illustrative.
Bid security% of the starting price1The share of the starting price you freeze for the bidding period. A guide, not a norm: check it against the act in force at the calculation date (checked 2026-11-17). The example value is illustrative.
Bid security termdays30How many days the bid security is unavailable to you. The example value is illustrative.
Performance security% of the starting price5The share of the starting price you freeze for the term of the contract. A guide, not a norm: check it against the act in force at the calculation date (checked 2026-11-17). The example value is illustrative.
Performance security termdays365From signing to the return of the security. The example value is illustrative.
Cost of money% per year22Your loan rate or required return. The example value is illustrative.
Reduction threshold for special measures% of the starting price25A reduction from this percent leads to tightened requirements for the participant. A guide, not a norm: check it against the act in force at the calculation date (checked 2026-11-17). The example value is illustrative.
Increase of the performance security at such a reductiontimes1.5By how many times the performance security grows: a guide at the date. A guide, not a norm: check it against the act in force at the calculation date (checked 2026-11-17). The example value is illustrative.

How it is calculated

StepFormula
Price floorcost ÷ (1 − target margin); with security: (cost + cost of security) ÷ (1 − target margin)
Permissible reduction1 − floor ÷ starting price
Security% of the starting price × term ÷ 365 × cost of money; at a reduction not below the threshold the performance security is multiplied

Worked numbers

Default values from the app; in the interactive version you enter your own.

Price floor
4.24 m ₽Cost ÷ (1 − target margin).
Permissible reduction from the starting price
15.2 %
Cost of bid security
904 ₽
Cost of performance security
55,000 ₽
Price floor including security
4.3 m ₽
Permissible reduction including security
14 %
Reduction of your bid
10 %
Margin of your bid
12.1 %(Price − cost − security) ÷ price.
Bid margin by depth of reduction, %
Bar chart: 0 % 20.9, 5 % 16.7, 10 % 12.1, 15 % 6.9, 20 % 1.1, 25 % −6.2−20−1001020300 %0 %Margin: 20.920.95 %5 %Margin: 16.716.710 %10 %Margin: 12.112.115 %15 %Margin: 6.96.920 %20 %Margin: 1.11.125 %25 %Margin: −6.2−6.230 %30 %Margin: −13.8−13.8%
Data as a table
MeasureMargin
0 %20.9
5 %16.7
10 %12.1
15 %6.9
20 %1.1
25 %−6.2
30 %−13.8

The bid at different reductions

ReductionPriceProfitMarginRegime
0 %5 m ₽1.04 m ₽20.9 %—
5 %4.75 m ₽794,096 ₽16.7 %—
10 %4.5 m ₽544,096 ₽12.1 %—
15 %4.25 m ₽294,096 ₽6.9 %—
20 %4 m ₽44,096 ₽1.1 %—
25 %3.75 m ₽−233,404 ₽−6.2 %special measures
30 %3.5 m ₽−483,404 ₽−13.8 %special measures

A specialist check is needed. Rates, thresholds, terms and tariffs here are entered as guides as of 2026-11-17: check each value against the act in force at the calculation date. The calculation is arithmetic and draws no legal conclusions.

What to do with the result: do not cut the price deeper than the floor including security and keep a reserve for performance costs; the cost of security is money frozen, not a free guarantee. Check the requirements of the procurement laws with a procurement specialist. A typical mistake: cutting the price below the floor to win and ignoring the cost of security.

Nuances and limits

  • Cutting the price below the floor.
  • Ignoring the cost of security.
  • Ignoring tightened requirements at a deep reduction.

Terms used