End-to-end cash gap: from the factory deposit to the buyer’s money
Calculates for how many days the brand’s cash is “frozen” from the factory deposit to the buyer’s payment, what amount is needed at the peak and what financing the gap costs.
At a glance
- What question does it answer?
- How many days and what amount of cash are “frozen” from the factory deposit to the buyer’s payment and what it costs.
- What data is needed?
- The factory order amount, deposit share, production, delivery and receiving times.
- How to read the result?
- For wholesale apparel the end-to-end gap is the sum of production, shipping, receiving and buyer credit; count it from your contracts. Shorten it with the cheapest lever: buyer prepayment, production time, the deposit share, buyer credit. Check the peak amount against “Cash flow”. Example on the default values: A RUB 12m factory order with a 30% prepayment, 45 days of production, 25 of delivery, 10 of receiving and a 60-day buyer delay: the end-to-end gap is 140 days and cash is frozen 108.5 days on average. The peak need is RUB 12m and financing the gap at 18% costs RUB 642,082. If the cash peak is above your available limit, cut production time, the prepayment share or the buyer delay. Next: “Monthly cash flow and cash gap” and “Overdraft, factoring or inventory loan: which is cheaper”.
Why and how to reason
Between paying the factory and receiving money from the buyer a lot of time passes, and all this time you finance the order. The gap consists of consecutive stages: production, delivery, receiving, buyer’s credit. Their days add up because they follow one after another. If the buyer makes a prepayment, part of the gap is closed.
Peak cash is how much you will have put in by the time of largest payments. The financing cost is computed per payment: amount x days until revenue x rate / 365, because the prepayment lies longer than the balance.
Example. A factory order of RUB 12 m, prepayment 30% = RUB 3.6 m on day 0, balance RUB 8.4 m on day 45. The gap is 45 + 25 + 10 + 60 = 140 days. Cash returns with revenue of RUB 26 m. Financing (3.6 x 140 + 8.4 x 95) x 0.18 / 365, about RUB 0.64 m. Revenue to order is 2.17: the cost of money is small compared with the result.
When to use it
Reach for it when placing a factory order and before a season, to arrange financing in advance. It helps understand what a long chain costs and whether it can be accelerated. Assumption: stage durations are known. If delivery is delayed, the gap grows. For many runs a year compute the total need in “Cash flow”. Especially important for collections with a long production cycle and imports.
How to read the result
A gap of 140 days is more than four months during which money does not work. A peak of RUB 12 m is the sum you must find. Compare the financing cost (RUB 0.64 m) with the run’s margin: if it eats a noticeable part, you need to shorten the term or obtain a prepayment. Speeding up production or delivery by 10 days will reduce the gap and cost. Decision: choose a financing method (own money, loan, buyer prepayment) and shorten the longest stages. Find the longest stage and ask whether it can be shortened without losing quality. Also check that the buyer’s prepayment really reduces the peak and not only the term: sometimes its amount is too small.
Common mistakes
Typical trap: forgetting receiving and preparation for shipment; counting the buyer’s credit from the order date rather than shipment; not including the buyer’s prepayment; ignoring delivery delays. Also: taking a deposit rate rather than a loan rate. Also: not including customs payments that are made before the sale.
What data is needed?
- The factory order amount, deposit share, production, delivery and receiving times.
- Revenue from the run and the buyer’s credit; optionally his prepayment.
- The cost of capital.
- Where to take it: the order amount and prepayment share from the factory contract; production, delivery and receiving times from the production and logistics schedule (WMS, warehouse data); revenue and delay from buyer terms. Add the stages in order: prepayment, production, delivery, receiving, delay.
Inputs
| Field | Unit | Value in the example | Meaning |
|---|---|---|---|
| Factory order amount | ₽ | 12,000,000 | The amount of the factory order that you pay. |
| Deposit to the factory | % of order | 30 | The remainder is paid before shipment from the factory. |
| Production | days | 45 | How many days production takes after payment or launch. |
| Delivery to your warehouse | days | 25 | How many days delivery to your warehouse takes. |
| Receiving and preparing for shipment | days | 10 | How many days receiving and preparing for shipment to the buyer take. |
| Revenue from this run | ₽ | 26,000,000 | The revenue from this shipment excl. VAT that you will receive from the buyer. |
| Buyer credit | days | 60 | The payment credit you give the buyer, in days. |
| Buyer prepayment (optional) | % of revenue | 0 | Arrives on the order day, before production. Optional. Empty: the field is ignored (counted as zero in sums). |
| Cost of capital | % a year | 18 | Illustrative 18% a year: replace it with your loan rate or the return you give up. |
How it is calculated
| Step | Formula |
|---|---|
| Gap | Production + delivery + receiving + buyer credit |
| Peak cash | Factory order − buyer prepayment |
| Financing | Rate ÷ 365 × Σ(payment × days until revenue arrives) |
Worked numbers
Default values from the app; in the interactive version you enter your own.
- End-to-end gap
- 140 daysFrom the factory deposit to the buyer’s payment.
- Average time cash is tied
- 109 days
- Cash needed at the peak
- 12 m ₽The factory order minus the buyer prepayment.
- Cost of financing the gap
- 642,082 ₽ · 5.4 % of order
- Revenue to order
- 2.17×
Cash timeline
| Event | Day | Cash |
|---|---|---|
| Deposit to the factory | 0 | −3.6 m ₽ |
| Balance to the factory before shipment | 45 | −8.4 m ₽ |
| Shipment to the buyer | 80 | — |
| Payment by the buyer | 140 | 26 m ₽ |
The gap can be shortened by a buyer prepayment, production time, the deposit share and the buyer credit. Each 30 days of gap at your rate costs about 1.5 % of the amount. Check in “Cash flow” whether cash is enough at the peak.
Nuances and limits
- Do not forget customs and delivery: they increase the amount to pay before the sale.
- Gaps of several runs overlap: calculate the peak cash for the season, not for one run.
- Include customs and delivery in the sum to be paid before the sale.
- Batches overlap: calculate the cash peak by season.