Yield cascade across stages
Multiplies the yields of four stages (cutting, sewing, quality control, packing) into a rolled yield, counts how many pieces to launch to get the required number of good ones and the cost of losses at each stage at the accumulated cost. Compares with a variant in which part of the QC rejects can be reworked.
At a glance
- What question does it answer?
- How many to launch to get the required good pieces and where money is lost.
- What data is needed?
- Yields of four stages.
- How to read the result?
- The rolled yield, the launch and the stage with the largest losses. Example on the default values: Rolled yield: 87.99%; Launch for the required good pieces: 5,682; Launch rounded up: 5,683; Losses without rework, pcs: 683. The figures are illustrative: enter your own to see your result.
Why and how to reason
Yield multiplies across stages. In the example 98%, 96%, 94% and 99.5% give a rolled 87.99%: for 5,000 good pieces launch 5,682 pieces (5,683 rounded up). If half of the QC rejects are reworked, the yield is 90.80%, the launch 5,507.
When to use it
Apply when counting the launch for an order and when agreeing the defect allowance with a factory.
How to read the result
Look at the rolled yield, the launch and the stage with the largest losses in money, not in pieces.
Common mistakes
They take an average yield instead of the yield by stage and leave fabric defects out of cutting.
What data is needed?
- Yields of four stages.
- Accumulated cost.
- Target and rework share.
Inputs
| Field | Unit | Value in the example | Meaning |
|---|---|---|---|
| Cutting | % | 98 | The share of good pieces after cutting, including fabric defects. The example value is illustrative. |
| Sewing | % | 96 | The share of good pieces after sewing. The example value is illustrative. |
| Quality control | % | 94 | The share of pieces that pass inspection the first time. The example value is illustrative. |
| Packing | % | 99.5 | The share of pieces without damage in packing. The example value is illustrative. |
| After cutting | ₽ | 650 | Fabric, trims and cutting per piece. The example value is illustrative. |
| After sewing | ₽ | 1,050 | With the sewing labor. The example value is illustrative. |
| After quality control | ₽ | 1,100 | With inspection. The example value is illustrative. |
| After packing | ₽ | 1,150 | The full cost of the finished piece. The example value is illustrative. |
| Good pieces needed | pcs | 5,000 | The customer order or the output plan. The example value is illustrative. |
| The share of QC rejects that can be reworked | % | 50 | The share of pieces rejected by QC that are accepted after rework. The example value is illustrative. |
| Cost of reworking a piece | ₽ | 150 | Optional: labor and material for correction. The example value is illustrative. |
How it is calculated
| Step | Formula |
|---|---|
| Rolled yield | cutting yield × sewing yield × QC yield × packing yield |
| Launch | required good pieces ÷ rolled yield |
| QC yield with rework | QC yield + (1 − QC yield) × rework share |
| Losses of a stage | pieces at the stage input × (1 − yield) × the accumulated cost at the exit of the stage |
Worked numbers
Default values from the app; in the interactive version you enter your own.
- Rolled yield
- 87.99 %The product of stage yields.
- Launch for the required good pieces
- 5,682Target ÷ rolled yield, before rounding.
- Launch rounded up
- 5,683
- Losses without rework, pcs
- 683
- Losses without rework, RUB
- 689,474 ₽
- Stage with the largest losses
- QC: 352,828 ₽
- Rolled yield with rework
- 90.8 %
- Launch with rework
- 5,507
- Losses with rework, RUB
- 498,086 ₽
- Net effect of rework
- +168,076 ₽
- Without rework
- With rework
Data as a table
| Measure | Without rework | With rework |
|---|---|---|
| Cutting | 73.9 | 71.6 |
| Sewing | 234 | 227 |
| QC | 353 | 171 |
| Packing | 28.9 | 28.9 |
Stages: yield, losses in pieces and money
| Stage | Yield | Losses, pcs | Losses, RUB | Yield with rework | Losses with rework, RUB |
|---|---|---|---|---|---|
| Cutting | 98 % | 114 | 73,869 ₽ | 98 % | 71,585 ₽ |
| Sewing | 96 % | 223 | 233,882 ₽ | 96 % | 226,649 ₽ |
| QC | 94 % | 321 | 352,828 ₽ | 97 % | 170,958 ₽ |
| Packing | 99.5 % | 25 | 28,894 ₽ | 99.5 % | 28,894 ₽ |
Reworking 50 % of QC rejects cuts the launch by 176 pcs and the losses by 191,388 ₽; the rework costs 23,312 ₽, the net effect is 168,076 ₽.
What to do with the result: put the launch, not the number of good pieces, into the order and write the defect allowance into the contract (AQL). A typical mistake: taking an average yield instead of the yield by stage and leaving fabric defects out of cutting.
Nuances and limits
- Taking an average yield.
- Leaving fabric defects out of cutting.
- Ignoring the cost of rework.