The 13-week cash plan

The balance by week from receipts, payments, payroll and taxes, the first week below the minimum and the gap in a stress.

both Stock and cash

Open interactively →

About the topic

Profit is not cash. A company can be profitable on paper and stop because of an empty account: goods bought in January, paid to the factory in February, sold in March, and the buyer’s money arrives in April. Profit shows the result of a period, while cash moves on payment dates. A 13-week plan (a quarter) translates the budget into the language of those dates.

Why a brand or retailer needs this. The decisions are: in which week the balance drops below the safe minimum and by how much, whether the credit limit suffices, which payments can be shifted without breaching contracts, what cushion to keep and what to do about a gap: speed up receipts, move payments or borrow. For a brand with factory prepayment and a long cycle a gap appears regularly, and it is better to see it 6–8 weeks ahead than three days ahead.

How to reason. The closing balance of a week equals the opening balance plus receipts minus payments. That is simple; the hard part is putting each payment into the right week. Receipts depend on the channel: platforms pay out with a delay, wholesale has deferred payment, retail brings cash on the sale day (acquiring arrives in 1–3 days). Payments are tied to contracts and the calendar: factory prepayment, rent, salary (advance and settlement), taxes, the collection purchase.

An illustrative example. Balance RUB 8m, minimum balance RUB 3m. In weeks 1–3 receipts are 2m, payments 1.5m: the balance rises to 9.5m. In week 4 the factory payment is 9m: balance 9.5 + 2 − 1.5 − 9 = RUB 1m, below the minimum by RUB 2m. That is a gap, visible three weeks ahead. Now a stress: buyers pay two weeks later and RUB 4m of receipts shift: the balance is minus RUB 3m. The gap grows from 2 to RUB 6m.

Where to start. Build a payment calendar for 13 weeks by dates, then receipts by channel with terms. Peaks BS, IS, AS, SO (before the sale, in the sale, after, the final clearance; your company may use different names) go into their own weeks. Typical traps: planning cash by profit, putting taxes in the accrual month, keeping no minimum balance, not including the factory prepayment, updating the plan monthly instead of weekly.

Key ideas

Balance by week

The closing balance of a week equals the opening balance plus receipts minus payments. In the example: 8 → 8.5 → 9.0 → 9.5 → RUB 1.0m in the factory payment week. The first week below the minimum (RUB 3m) and the size of the gap (RUB 2m) are the main result.

Minimum balance as a cushion

The minimum covers a bank payment delay, an acquiring outage, an unexpected payment. Its size depends on the credit limit, the key rate and the season: for example two weeks of expenses without receipts. If weekly payments are RUB 1.5m, a RUB 3m cushion covers two weeks.

Taxes and salary are tied to dates

Salary is paid at least every half-month (Art. 136 of the Labor Code), taxes are paid per the single tax payment calendar. If quarterly VAT is RUB 4.5m, it is split into three payments of RUB 1.5m in the months after the quarter. Putting it in the accrual month means being wrong by weeks.

Stress: delay and shortfall

The test repeats the calculation with receipts delayed by two weeks and with a shortfall, for instance minus 15% of revenue. In the example the delay turns a RUB 2m gap into a RUB 6m gap. It shows whether the limit suffices: if the limit is RUB 5m it does not cover the stress, and a decision is needed in advance.

What closes a gap

Three levers: speed up receipts (a discount for prepayment, invoicing earlier, settlements with a platform), shift payments (agree a deferral or parts) and a loan. The first two are free or cheap but limited by contracts; a loan costs more. Determine how much of the gap each closes.

The plan rolls

Each week you add a new thirteenth week, replace the forecast with actuals and revise the rest. The horizon is thus always 13 weeks. A plan updated monthly is blind three weeks ahead by the end of the month.

The levers of a plan live in their own weeks: a supplier deferral moves money rather than creating it

Without measures the cash RUB 9 million and a spend of RUB 900,000 a week take the balance below the reserve RUB 3 million in week 7. With expected measures the minimum over 13 weeks is RUB 5.21 million, and with conservative ones (the effect lower by 25%) RUB 3.17 million: a margin over the reserve of RUB 170,750. A supplier deferral brings RUB 2.16 million in week 2, but the repayment in week 9 takes the same sum, so over 13 weeks its contribution is zero, and the line with measures falls by RUB 2.64 million in week 9. The balance and gap by week are counted by the base 13-week calculation; here only the levers are added: the strongest of them, selling dead stock, gives an expectation of RUB 2.4 million.

Formula: Lever expectation = (one-off sum + weekly effect × weeks) × probability − cost

What to do: Show the cash path in two variants, expected and conservative, and write the repayment of a deferral as a separate line in the right week.

Think first: A deferral gives +RUB 3.6 million in week 2. Why does the line with measures fall by almost RUB 2.6 million in week 9?

Answer: The repayment falls in week 9: −3.6m × 60% = −RUB 2.16 million, plus the weekly spend. Over 13 weeks the deferral contributes zero: it is a postponement of a payment.

How to work through it

  1. Build a payment calendar for 13 weeks by dates: factory, rent, salary, taxes, purchasing, advertising.
  2. Build a receipts calendar by channels and terms: retail, platforms, wholesale, site.
  3. Set the opening balance, the minimum balance and the credit limit.
  4. Calculate the balance by week and find the first week below the minimum and the size of the gap.
  5. Repeat with delayed receipts and a shortfall; compare the gap with the limit.
  6. Decide how to close the gap: receipts, shifting payments, a loan; name owners and deadlines.
  7. Each week replace the forecast with actuals and add a new week.

Where to start

Start with “The 13-week cash plan”, then check by month in “Monthly cash flow”. Calculations of the topic in order: “The 13-week cash plan: balance, gap and stress”, “Unified tax account calendar: the month’s payment, what to deposit and penalties”, “A 13-week cash plan with levers: when the reserve breaks and what holds it”. See also (their primary topic is another one): “Monthly cash flow and cash gap”, “End-to-end cash gap: from the factory deposit to the buyer’s money”, “Profit versus cash: where the difference went”.

Calculations in this topic

  • The 13-week cash plan: balance, gap and stress

    Week by week calculates the cash balance from receipts and payments, finds the first week below the minimum balance and the size of the gap, then repeats the calculation with delayed and short customer receipts.

    In which week cash falls below the minimum, by how much and whether a credit line will do if customers pay late.

  • Unified tax account calendar: the month’s payment, what to deposit and penalties

    Spreads the year’s taxes and contributions into one payment by month, shows the heaviest month, how much must be deposited on the unified tax account by the due date given the balance and what the penalty on an arrear comes to at a given key rate and number of days late. Helps put tax dates into the cash plan.

    What unified payment awaits each month, how much to deposit on the unified tax account by the due date and what the penalty comes to if the date is missed.

  • A 13-week cash plan with levers: when the reserve breaks and what holds it

    Spreads the brand’s cash over 13 weeks: the path without measures at a given weekly outflow, the path with the expected effect of levers (one-off receipts and weekly effects times probability, less cost) and a conservative path with a shortfall allowance. Shows the week when cash falls below the reserve in each path, the lowest balance, the strongest lever and how much is missing to the reserve if only part of the measures works.

    In which week cash falls below the reserve without measures, with expected and with conservative measures and how much money is missing.

  • Monthly cash flow and cash gap

    From monthly receipts and payments calculates the cash balance, the tightest month and the shortfall against a safe minimum.

    In which month cash falls below the safe minimum and how much must be raised or deferred.

  • End-to-end cash gap: from the factory deposit to the buyer’s money

    Calculates for how many days the brand’s cash is “frozen” from the factory deposit to the buyer’s payment, what amount is needed at the peak and what financing the gap costs.

    How many days and what amount of cash are “frozen” from the factory deposit to the buyer’s payment and what it costs.

  • Profit versus cash: where the difference went

    Lays out the path from profit to the change in cash: depreciation, growth in stock, receivables and payables, equipment purchases, loans. Shows which line ate the cash despite a positive profit.

    Why is cash short despite profit and which line took it.

Self-check questions

  • In which week will the balance fall below the minimum and by how much?
  • What minimum balance do I hold and what is it made of?
  • Does the credit limit suffice in a stress with delay and shortfall?
  • Which payments can I shift without breaching contracts or incurring penalties?
  • What part of the gap is closed by speeding up receipts and what only by a loan?
  • Are taxes and salary placed in the due weeks, not the accrual month?
  • Are the factory prepayment and the collection purchase included in the payment week?
  • How often do I replace the forecast with actuals and roll the window?

Knowledge check

Multiple-choice questions. The correct answer and the explanation follow each question.

  1. Starting cash RUB 6 million, minimum balance RUB 3 million. A 4-week plan: receipts of RUB 2 million and payments of RUB 2.5 million a week. Stress: receipts arrive a week later and 10% lower, payments do not change. What is the lowest balance under stress?

    • A. RUB 1.4 million in week 4: RUB 1.6 million short of the minimum
    • B. RUB 2.0 million in week 4: RUB 1.0 million short of the minimum
    • C. RUB 3.2 million in week 4: the minimum holds
    • D. RUB 4.0 million in week 4: the minimum holds

    Correct answer: A. RUB 1.4 million in week 4: RUB 1.6 million short of the minimum. Under stress the receipt of week i equals the plan of week i − 1 times 0.9: RUB 0, then 1.8, 1.8 and 1.8 million. The balance (RUB million): 6 − 2.5 = 3.5; 3.5 + 1.8 − 2.5 = 2.8; then 2.1 and 1.4. The minimum is RUB 1.4 million in week 4, RUB 1.6 million short of 3 million. 2.0 (1.0 short) comes from counting only the delay, 3.2 from counting only the 10% shortfall and forgetting the delay, and 4.0 is the plan balance without stress (6 + 4 × 2 − 4 × 2.5).

  2. Cash RUB 9 million, a spend of RUB 900,000 a week, a reserve of RUB 3 million. In which week is the reserve breached without measures?

    • A. In week 3
    • B. In week 7
    • C. In week 10
    • D. In week 13

    Correct answer: B. In week 7. (9 m ₽ − 3 m ₽) ÷ 900,000 ₽ = 6.7 weeks of margin, so the reserve is breached in week 7. Covered in: The levers of a plan live in their own weeks: a supplier deferral moves money rather than creating it.

  3. With conservative measures (the effect 25% lower) the minimum balance is RUB 3.17 million. What does it mean for the reserve of RUB 3 million?

    • A. The reserve is breached by 170,750 ₽
    • B. The margin is large, the measures can be skipped
    • C. The reserve holds with a margin of RUB 170,750: nearly all measures are needed
    • D. This minimum belongs to the path without measures

    Correct answer: C. The reserve holds with a margin of RUB 170,750: nearly all measures are needed. RUB 3.17 million − RUB 3 million = RUB 170,750: the margin is thin, and if execution turns out a few percent worse the reserve will be breached. Covered in: The levers of a plan live in their own weeks: a supplier deferral moves money rather than creating it.

  4. A supplier deferral gives RUB 3.6 million in week 2, the repayment is RUB 3.6 million in week 9, the probability is 60%. What is the contribution of the deferral to cash by week 13?

    • A. +2.16 m ₽
    • B. +3.6 m ₽
    • C. −2.16 m ₽
    • D. Zero: it is a postponement of a payment, not a saving

    Correct answer: D. Zero: it is a postponement of a payment, not a saving. RUB 2.16 million in week 2 and −RUB 2.16 million in week 9 sum to zero. A deferral wins time, not money, and it has to be shown together with the repayment. Covered in: The levers of a plan live in their own weeks: a supplier deferral moves money rather than creating it.

  5. Which lever is the strongest by the expected effect?

    • A. Moving purchases to the next season: RUB 1.3 million
    • B. Keep advertising only in paying channels: RUB 1.4 million
    • C. Sell dead stock through outside channels: RUB 2.4 million
    • D. Hiring and bonus freeze: RUB 912,000

    Correct answer: C. Sell dead stock through outside channels: RUB 2.4 million. Selling dead stock: RUB 3 million × 80% = RUB 2.4 million, no cost. The weekly levers are smaller because they accrue week by week and have a lower probability. Covered in: The levers of a plan live in their own weeks: a supplier deferral moves money rather than creating it.

Common mistakes

  • Planning cash by profit rather than by payment weeks. Consequence: the gap is seen three days ahead, not six weeks. How to avoid: build the calendar by contract dates.
  • Placing taxes in the accrual month rather than the due week. Consequence: a wrong balance in the weeks that matter. How to avoid: check the tax calendar under the single tax account rules.
  • Not keeping a minimum balance. Consequence: any delay becomes a cash gap. How to avoid: set a cushion and measure the gap against it.
  • Not including factory prepayment and the collection purchase in the payment week. Consequence: the largest payment is invisible. How to avoid: place by the contract schedule.
  • Updating the plan monthly. Consequence: in the third week you cannot see a future gap. How to avoid: a weekly cycle replacing forecast with actuals.
  • Mistake: A supplier deferral is written as a saving

    What it costs: The repayment arrives in week 9 and the gap returns The line with measures falls by RUB 2.64 million in week 9, and decisions made on the overstated balance will have to be reversed.

    How to avoid: Show a deferral as a pair of lines: received and repaid Write the repayment in the right week and check the minimum balance after it.

    What it looks like (illustrative figures): In a plan a deferral of RUB 2.16 million in week 2 without the repayment lifts the minimum balance from RUB 5.21 million by RUB 2.16 million.

Russia and the EAEU

Taxes. Since 2023 taxes and contributions are paid as a single tax payment on the single tax account (ENS) with a notification of the calculated sums; payment dates usually fall on the 28th, but check the dates and procedure in the calendar for your year. Quarterly VAT is paid in three equal parts in the months after the quarter. The VAT rate is 22% from 01.01.2026; on the simplified regime with income above RUB 20m VAT appears (228-FZ). Corporate income tax 25%.

Salary and contributions. Salary is paid at least every half-month (Art. 136 of the Labor Code); put the advance and the settlement in the calendar as separate lines. Contributions go through the ENS.

Receipts. Acquiring arrives in 1–3 banking days, platform payouts follow the platform’s schedule (terms in your contract; the platform economy law No. 289-FZ applies from 01.10.2026), wholesale on deferral terms. Banks: the overdraft limit and the key rate set the price of a gap. Payments abroad fall under currency control (173-FZ), and transfer times through correspondent banks add weeks in transit. Check the dates with an accountant.

For a company operating in several countries the 13-week plan is kept by currency separately and then consolidated: a rouble balance, a balance in tenge, Belarusian roubles, drams, soms and so on. The rate between them moves the overall balance, so add an exchange-rate scenario.

Tax calendars and payment dates in Belarus, Kazakhstan, Armenia and Kyrgyzstan are their own (indicative as of 14.11.2026, check the text of the act). As a guide for VAT rates by country are on the page “EAEU and CIS countries” (as of 14.11.2026). When goods move between union countries VAT under Annex 18 is paid in the destination country, usually by the 20th of the month following the month of import (check with an accountant). Settlements in national currencies may follow the terms and rules of your banks.

Categories and audiences

Apparel
For apparel: the largest payment is the collection purchase 3–6 months before sales, so the gap usually sits before the season. Cash returns at the height of the season and the sale. Count returns after sales as an outflow. Match the payment schedule with contract dates.
Footwear
If it is footwear: a long cycle (production, delivery, fitting) and high cost, so large prepayments and a slow return of cash. Leftover seasonal pairs freeze cash for long; the clearance timing directly shifts inflow weeks. Check the payment term of each lot.
Accessories
On accessories: a shorter cycle, smaller lots, a lower basket; a payment per lot is smaller while inflow to December and spring holidays is much higher. A gap is likelier in late autumn (buying for gifts) and after holidays.
Kids
In children’s wear: strong inflow in August before school and in December, with purchasing several months earlier. Weeks with receipt peaks must be placed precisely; a season shift of a week moves the inflow.
Men
In a men’s line payments gather ahead of the outerwear and footwear season: prepayment to the factory falls over several weeks in a row and creates a trough in the 13-week schedule. Place these payments by date and fit the basics (shirts, jeans) into smaller weekly payments. This shows in which week the cushion is thinnest.
Women
In a women’s line cash is moved by platforms and returns: money for shipments arrives on the payout schedule, while returns after a sale go out in the next weeks. In the 13-week plan keep separate lines: platform payouts on their schedule and returns after each promotion. Check the payout schedule every week.

Questions this topic answers

  • In which week does the balance fall below the minimum and by how much?
  • Is the credit line enough for the gap in the stress?
  • Which payments can be shifted without breaking contracts?
  • What balance is needed as a cushion and what does it depend on: the limit, the key rate, the season?
  • Which part of the gap closes by speeding up customer payments and which only by a loan?

Key measures and terms

Study first

What next

Related: “Buying budget and cash”, “Cash and working capital”, “Owner’s cash and management dashboard”.