Lead time
Days from order placement to warehouse receipt; watch both the median and the worst quartile
- Formula
Days from order placement to warehouse receipt; watch both the median and the worst quartile- Unit
- days
- Aggregation rule
- Weighted average
- Source system
- ERP and accounting system; Warehouse and stock system
- Owning role
- Head of production / sourcing
- Frequency
- Per season
Passport
- Grain
- Order × delivery
- Numerator
- Sum of (days to arrival × order size)
- Denominator
- Sum of order sizes
- At zero or no data
- No orders: “—”.
- Limits
- Counted from the order date to goods-in at the warehouse. Look at the median and the worst quartile, not only the average. The weight is the order size.
- Check example
- Lead time of order 1, days: 42; Size of order 1, units: 1000; Lead time of order 2, days: 38; Size of order 2, units: 600; Lead time of order 3, days: 46; Size of order 3, units: 400.
(a*x+c*y+d*z)/(x+y+z). Result: 41.6 days - Related metrics
Version 1.0 · valid from 2026-11-16 · checked 2026-11-16
Related pages
- Term: Lead time
- Calculation: Collection calendar: critical path and slack
Definition
The time from placing an order until goods arrive in the warehouse.
The longer the lead time, the more safety stock and the earlier the order decision.