Half delivery date
The date when the cumulative delivery at purchase prices reached 50% of the confirmed; shown in days from the first delivery
- Formula
The date when the cumulative delivery at purchase prices reached 50% of the confirmed; shown in days from the first delivery- Unit
- days
- Aggregation rule
- Average over dates
- Source system
- ERP and accounting system; Warehouse and stock system
- Owning role
- Head of buying / buyer
- Frequency
- Monthly
Passport
- Grain
- Batch or season goods × supplier; cumulative delivery at purchase prices
- At zero or no data
- No half-delivery date (cumulative delivery has not reached 50%): show “—”.
- Limits
- Counted from cumulative delivery at purchase prices up to 50% of the confirmed. Shown in days from the first delivery: the larger, the later the goods arrive and the lower the early sales pace should be.
- Check example
- Day of the half delivery from the season start: 41; Day of the first delivery from the season start: 12.
a-b. Result: 29 days - Related metrics
Version 1.0 · valid from 2026-11-16 · checked 2026-11-16
Related pages
- Term: First and half delivery dates
- Calculation: Buying plan from revenue backwards: revenue → cost → order
Definition
The first delivery is the earliest receipt date of the season goods, the half delivery is the date when the cumulative delivery at purchase prices reached 50% of the confirmed, the last is the latest date.
Count sales from the first delivery, assess the pace from the half one: a late delivery then does not understate the pace.