Plan versus actual, variance

Plan versus actual, variance: the difference between actual and plan for a line. For income minus is worse, for costs plus is worse, so the sign must be read by effect on profit; the variance is analyzed by cause: volume, price, one-offs.

Cash and capital

Open interactively →

Formula

Variance = actual − plan; for costs the effect on profit = plan − actual

How to read

Suppose planned revenue is RUB 10 million and actual RUB 9.2 million: variance −RUB 0.8 million (−8%); costs plan 4m and actual 4.3m: effect on profit −0.3m. Analyze first the line with the biggest harm to profit.