Worked example: a calendar counted back from the in-store date
A brand wants sales to start on 1 September 2027 and counts the deadlines backwards. The stage durations are illustrative.
Figures
- Fabric order
- 30 days
- Production
- 40 days
- Sea transport
- 35 days
- Customs and warehouse
- 10 days
- Total and the last date to order fabric (calculation)
- 115 days: order no later than 9 May 2027
Lesson
Any delay in a stage on the critical path moves the shelf date by the same number of days. Put a buffer into the calendar right away, for example 10–14 days, and record real durations for each supplier.