Worked example: a calendar counted back from the in-store date

A brand wants sales to start on 1 September 2027 and counts the deadlines backwards. The stage durations are illustrative.

Example illustrative example

Open interactively →

Figures

Fabric order
30 days
Production
40 days
Sea transport
35 days
Customs and warehouse
10 days
Total and the last date to order fabric (calculation)
115 days: order no later than 9 May 2027

Lesson

Any delay in a stage on the critical path moves the shelf date by the same number of days. Put a buffer into the calendar right away, for example 10–14 days, and record real durations for each supplier.