Worked example: reorder point and safety stock
A store replenishes a basic style with a 9-day delivery. Sales, lead time and safety stock are illustrative; there is no real data behind them.
Figures
- Sales per day
- 12 pcs
- Delivery time
- 9 days
- Safety stock
- 36 pcs
- Reorder point (calculation)
- 12 × 9 + 36 = 144 pcs
- Stock now
- 160 pcs: (160 − 144) / 12 ≈ 1.3 days left to the reorder point
Lesson
Order when stock falls to the point, not when it runs out: delivery time and safety stock are part of the point. If the lead time grows to 12 days, the point becomes 12 × 12 + 36 = 180, and an order at 160 is already late.