A brand adds up the stage durations of the collection lifecycle. The durations are illustrative.

Example illustrative example

Open interactively →

Figures

Design and tech pack
21 + 7 days
Samples and approval
28 + 7 days
Production and delivery
45 + 30 days
Total (calculation)
138 days, about 20 weeks

Lesson

All stages run one after another, so a 10-day delay in samples moves delivery by the same 10 days. Look for stages that can run in parallel, such as buying fabric during sampling.