Worked example: a lead-time stack from idea to delivery
A brand adds up the stage durations of the collection lifecycle. The durations are illustrative.
Figures
- Design and tech pack
- 21 + 7 days
- Samples and approval
- 28 + 7 days
- Production and delivery
- 45 + 30 days
- Total (calculation)
- 138 days, about 20 weeks
Lesson
All stages run one after another, so a 10-day delay in samples moves delivery by the same 10 days. Look for stages that can run in parallel, such as buying fabric during sampling.